INSP - Final | 8/27/1998 | 8/28/1998 | 8/28/1998 | A | PART |
|
|
|
made ok for temp signed the temp col
|
INSP-Final Inspection | 8/25/1998 | 8/27/1998 | 8/27/1998 | P | PART |
Joe Tawney
|
|
|
08/27/98 406 - sterling ###-#### as per joe tawney/2:00 OK ON ALARM TEST
|
INSP - Framing/Rough-in | 8/26/1998 | 8/26/1998 | 8/26/1998 | P | PART |
|
|
|
08/26/98 338 - ok to drop in tiles
|
INSP - Final | 7/30/1998 | 7/30/1998 | 7/30/1998 | P | PART |
Jim Storey
|
|
|
07/30/98 301 - TCO -TEMP C OF O ISSUED w/c/n for p.paine to check
|
INSP - Framing/Rough-in | 7/15/1998 | 7/16/1998 | 7/30/1998 | A | NR |
|
|
|
07ID CEILING MALCOM EMERY ###-####
|
INSP - Final | 7/24/1998 | 7/27/1998 | 7/27/1998 | P | NR |
|
|
|
07/27/98 338 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP-Final Inspection | 7/24/1998 | 7/27/1998 | 7/27/1998 | P | PASS |
Joe Tawney
|
|
|
07/27/98 406 - 1 o'clock with perry gary ###-#### unit 110 REINSP OK FOR PERM OCC
|
INSP-Final Inspection | 7/17/1998 | 7/21/1998 | 7/21/1998 | P | FAIL |
Joe Tawney
|
|
|
07/21/98 406 - gary ###-#### FINAL FAIL SPKLR HD & HEAT DET IN ELEV PIT STILL NEED TO TEST LIGHTS ì
|
INSP - Framing/Rough-in | 7/1/1998 | 7/2/1998 | 7/2/1998 | A | PART |
|
|
|
07/02/98 338 - ceiling grid inspection something about seimic wires Mac ###-#### made ok for the parts of the 2nd and 3nd floors
|
INSP - Wall cover | 5/12/1998 | 5/12/1998 | 5/12/1998 | | FAIL |
|
|
|
/ / 338 - FIRE CAULK ASSYS FAIL
|
INSP - Framing/Rough-in | 4/2/1998 | 4/2/1998 | 4/2/1998 | | PART |
|
|
|
/ / 338 - bsmt, 1st, 2nd, 3rd floor misc. framing ok to cover int wall
|