INSP - Final | 3/9/1999 | 3/9/1999 | 3/10/1999 | P | PASS |
Wes Worcester
|
|
|
03/09/99 342 - chris ###-#### c/c issued
|
INSP - Grading Inspection | 2/18/1999 | | 2/18/1999 | | BOND |
Rita DeYoung
|
|
|
Minor fine grading and revegetation is yet to be completed. For this the engineer has recommended a $600.00 bond. When this is submitted the grading and drainage is conditionally approved.
|
INSP - Final | 1/21/1999 | 1/22/1999 | 1/21/1999 | A | FAIL |
Wes Worcester
|
|
|
01/22/99 342 - 5 DAY NOTICE ISSUED
|
INSP-Final Inspection | 1/15/1999 | 1/15/1999 | 1/15/1999 | P | FAIL |
Rick Jackson
|
|
|
lonnie- ###-#### fn fire insp leak at main riser; sprinkler flow not tied to smoke detectors
|
INSP - Foundation | 10/8/1998 | 10/9/1998 | 10/9/1998 | A | FAIL |
Wes Worcester
|
|
|
10/09/98 342 - COLE ###-#### pouring w/o inspection, c/n posted, footing do not cover posted on rebar
|
INSP - Foundation | 10/7/1998 | 10/8/1998 | 10/8/1998 | A | NR |
Wes Worcester
|
|
|
10/08/98 342 - COLE ###-#### ì
|
INSP - Energy code compliance | 8/13/1998 | 8/14/1998 | 8/14/1998 | P | NR |
Wes Worcester
|
|
|
08/13/98 342 - insulation cole ###-####
|
INSP - Framing/Rough-in | 8/11/1998 | 8/12/1998 | 8/12/1998 | A | PASS |
Wes Worcester
|
|
|
08/11/98 342 - early am ###-####
|
INSP - Framing/Rough-in | 8/11/1998 | 8/11/1998 | 8/11/1998 | P | NR |
Wes Worcester
|
|
|
08/11/98 342 - infintration package cole ###-####
|
INSP - Framing/Rough-in | 8/5/1998 | 8/7/1998 | 8/7/1998 | P | PART |
Wes Worcester
|
|
|
COLE ###-####
|
INSP - Framing/Rough-in | 8/7/1998 | 8/7/1998 | 8/7/1998 | | PASS |
Wes Worcester
|
|
|
08/07/98 342 - COLE ###-#### ì
|
INSP-Sprinkler Rough-in/Hydro | 8/4/1998 | 8/4/1998 | 8/4/1998 | P | PASS |
Rick Jackson
|
|
|
hydro okay
|
INSP - Framing/Rough-in | 7/17/1998 | 7/20/1998 | 7/20/1998 | A | PART |
Wes Worcester
|
|
|
07/20/98 342 - shear ok, roof ok to cover
|
INSP - Framing/Rough-in | 6/23/1998 | 6/24/1998 | 6/24/1998 | A | PASS |
Wes Worcester
|
|
|
06/24/98 342 - fireplace re-bar/ cole ###-####
|
INSP - Foundation | 6/17/1998 | 6/18/1998 | 6/18/1998 | A | PART |
Wes Worcester
|
|
|
06/18/98 342 - RE-BAR/ ###-#### 9am apt 2 frplcs ok so far
|
INSP - Foundation | 6/12/1998 | 6/15/1998 | 6/15/1998 | A | CANC |
Wes Worcester
|
|
|
06/15/98 342 - rebar inspection cole ###-####. cancelled by cole.
|
INSP - Foundation | 5/18/1998 | 5/18/1998 | 5/18/1998 | | PASS |
Wes Worcester
|
|
|
/ / 342 - fireplace rebar per resubmittal
|
INSP - Foundation | 5/18/1998 | 5/18/1998 | 5/18/1998 | P | NR |
Wes Worcester
|
|
|
05/18/98 342 - footer for fire place/ ###-#### cole erickson have not re will do in am and after approval will inspect
|
INSP - Foundation | 5/5/1998 | 5/6/1998 | 5/6/1998 | A | PART |
Wes Worcester
|
|
|
05/05/98 342 - COLE/###-#### - SCHEDULED WITH WES FOR 8.AM.
|
INSP - Foundation | 5/5/1998 | 5/6/1998 | 5/6/1998 | P | PASS |
Wes Worcester
|
|
|
05/05/98 342 - foundation steam walls/cole ###-####
|
INSP - Foundation | 4/28/1998 | 4/29/1998 | 4/30/1998 | P | PASS |
Wes Worcester
|
|
|
04/30/98 342 - COLE/ ###-#### - FOOTING INSP. EARLY PM.
|