INSP - Grading Inspection | 4/29/1999 | | 4/29/1999 | | PASS |
Rita DeYoung
|
|
|
Revegetation complete and $300 bond can now be released.
|
INSP - Final | 1/28/1999 | 1/28/1999 | 1/28/1999 | P | FAIL |
Wes Worcester
|
|
|
01/28/99 342 - PHIL ###-#### called and we need public works signed off
|
INSP - Grading Inspection | 1/28/1999 | | 1/28/1999 | | BOND |
Rita DeYoung
|
|
|
Grading and drainage are complete. Received approval from ACHD for storm drain connection to their system. Revegetation is not done and for this the engineer recommended a $300.00 bond. Upon receipt of this the grading and drainage is approved for final.
|
INSP - Energy code compliance | 9/21/1998 | 9/21/1998 | 9/21/1998 | P | PASS |
Wes Worcester
|
|
|
09/21/98 342 - phil ###-#### ì
|
INSP - Framing/Rough-in | 9/21/1998 | 9/21/1998 | 9/21/1998 | P | PASS |
Wes Worcester
|
|
|
09/21/98 342 - phil ###-#### ì
|
INSP - Framing/Rough-in | 9/16/1998 | 9/16/1998 | 9/16/1998 | | PART |
Wes Worcester
|
|
|
/ / 342 - engineering completed????will meet Phil at 8am
|
INSP - Framing/Rough-in | 9/15/1998 | 9/16/1998 | 9/16/1998 | A | NR |
Wes Worcester
|
|
|
09/16/98 342 - PHIL ###-#### 8am apt
|
INSP - Framing/Rough-in | 9/2/1998 | 9/3/1998 | 9/3/1998 | P | NR |
Wes Worcester
|
|
|
09/02/98 342 - PHIL ###-#### CALL BEFORE GOING
|
INSP - Framing/Rough-in | 9/1/1998 | 9/2/1998 | 9/2/1998 | P | FAIL |
Wes Worcester
|
|
|
09/02/98 342 - phil ###-#### members cut out at hold downs, bolts and na hgrs, no plan on site, no engineering on site
|
INSP - Foundation | 6/17/1998 | 6/18/1998 | 6/18/1998 | A | PASS |
Wes Worcester
|
|
|
06/18/98 342 - donny ###-####
|
INSP - Wall cover | 6/5/1998 | 6/5/1998 | 6/5/1998 | P | PASS |
Wes Worcester
|
|
|
06/05/98 342 - basement walls/ donny ###-####
|
INSP - Foundation | 5/28/1998 | 5/28/1998 | 5/28/1998 | | PASS |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Foundation | 5/27/1998 | 5/28/1998 | 5/28/1998 | A | NR |
Wes Worcester
|
|
|
05/28/98 342 - footing reinspect ###-####
|
INSP - Foundation | 5/21/1998 | 5/21/1998 | 5/21/1998 | | FAIL |
Wes Worcester
|
|
|
/ / 342 - 3-3:30 pm pulled off.....no phone call.....
|
INSP - Foundation | 5/20/1998 | 5/21/1998 | 5/21/1998 | A | NR |
Wes Worcester
|
|
|
05/21/98 342 - ###-#### footing
|