INSP - Final | 6/10/1998 | 6/11/1998 | 6/11/1998 | P | PASS |
Russ Owen
|
|
|
06/11/98 407 - final/ open george ###-####
|
INSP - Letter of compliance | 6/11/1998 | 6/11/1998 | 6/11/1998 | | PASS |
Russ Owen
|
|
|
/ / 407 - LC#
|
INSP - Letter of compliance | 6/11/1998 | 6/11/1998 | 6/11/1998 | | PASS |
Russ Owen
|
|
|
/ / 407 - LC#
|
INSP - Final | 6/8/1998 | 6/9/1998 | 6/9/1998 | P | FAIL |
Russ Owen
|
|
|
06/09/98 407 - need step out of garage and a landing .
|
INSP - Energy code compliance | 5/6/1998 | 5/6/1998 | 5/6/1998 | P | PASS |
Russ Owen
|
|
|
CONTRACTOR INDICATED WATSUN DOES NOT REQUIRE HIGH R AT GARAGE WALL / / 407 -
|
INSP - Energy code compliance | 5/5/1998 | 5/5/1998 | 5/5/1998 | | PART |
Russ Owen
|
|
|
05/05/98 407 - need high r required bettween house and garage wall.
|
INSP - Framing/Rough-in | 5/5/1998 | 5/5/1998 | 5/5/1998 | | PASS |
Russ Owen
|
|
|
/ / 407 - re insp.
|
INSP - Energy code compliance | 5/2/1998 | 5/4/1998 | 5/4/1998 | P | CANC |
Russ Owen
|
|
|
05/04/98 407 - contractor called to cancell.
|
INSP - Framing/Rough-in | 4/30/1998 | 5/1/1998 | 5/1/1998 | P | FAIL |
Russ Owen
|
|
|
george ###-####
|
INSP - Framing/Rough-in | 4/29/1998 | 4/30/1998 | 4/30/1998 | P | CANC |
Russ Owen
|
|
|
04/30/98 407 - GEORGE LATE PM ###-####
|
INSP - Foundation | 4/13/1998 | 4/13/1998 | 4/13/1998 | P | PART |
Russ Owen
|
|
|
04/13/98 407 - footings poured before inspection. No Approved plans or any plans on site.Set backs are tight 5' only on both sides the placement of the foundation walls needs to be correct.
|