INSP - Final | 1/19/1999 | 1/19/1999 | 1/19/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP - Final | 1/19/1999 | 1/19/1999 | 1/19/1999 | P | PASS |
Tom Arcoraci
|
|
|
01/19/99 408 - ###-#### TONY
|
Permanent Occupancy | | 1/19/1999 | 1/19/1999 | | DONE |
|
|
|
|
INSP - Final | 1/12/1999 | 1/12/1999 | 1/12/1999 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - REINSP FAIL FAX OF ALARM SIGNALS SENT 12/30/98
|
INSP-Final Inspection | 1/5/1999 | 1/6/1999 | 1/6/1999 | A | FAIL |
Joe Tawney
|
|
|
01/06/99 406 - TONY- ###-#### FN FIRE INSP REINSP FAIL SMOKE DET, BATTERY BACKUP. FAX OF ALARM SIGNALS
|
INSP-Final Inspection | 12/30/1998 | 12/31/1998 | 12/31/1998 | A | CANC |
Rick Jackson
|
|
|
CLINT- ###-#### FN FIRE contractor called and they will reschedule for next week, not ready
|
INSP-Final Inspection | 12/31/1998 | 12/31/1998 | 12/31/1998 | | CANC |
Rick Jackson
|
|
|
12/31/98 409 - CLINT- ###-#### FN FIRE contractor called and said he isn't ready and will reschedule for next w
|
INSP - Final | 12/29/1998 | 12/31/1998 | 12/30/1998 | A | PART |
Tom Arcoraci
|
|
|
12/31/98 408 - CLINT ###-#### ok for perm when others are signed perm
|
INSP-Final Inspection | 12/30/1998 | 12/30/1998 | 12/30/1998 | | PART |
Joe Tawney
|
|
|
12/30/98 406 - CLINT ###-#### REINSP OK FOR TEMP OCC PASSAGE BETWEENROOMS, FAX OF ALARM SIG, BAT BACK
|
INSP-Final Inspection | 12/10/1998 | 12/11/1998 | 12/11/1998 | A | FAIL |
Joe Tawney
|
|
|
12/11/98 406 - clint ###-#### fire ins per joe 8:30 FINAL FAIL ALARM SYSTEM, EXIT DOORS CLASSROOMS
|
INSP - Final | 12/7/1998 | 12/10/1998 | 12/11/1998 | A | FAIL |
|
|
|
12/11/98 338 - this is sent and done by 408
|
INSP - Final | 12/10/1998 | 12/11/1998 | 12/10/1998 | A | FAIL |
Tom Arcoraci
|
|
|
12/11/98 408 - clint- ###-#### fn insp occ no fire inspec
|
INSP - Final | 12/10/1998 | 12/10/1998 | 12/10/1998 | | FAIL |
Tom Arcoraci
|
|
|
12/10/98 408 - TONY ###-#### FN INSP not ready
|
INSP - Final | 12/10/1998 | 12/10/1998 | 12/10/1998 | | FAIL |
Tom Arcoraci
|
|
|
12/10/98 408 - TONY ###-#### FN INSP not ready
|
INSP-Final Inspection | 12/10/1998 | 12/10/1998 | 12/10/1998 | | CANC |
Joe Tawney
|
|
|
12/10/98 406 - ###-####- CANCEL RESCHEDULED TO 12/11/98
|
INSP - Final | 12/4/1998 | 12/7/1998 | 12/7/1998 | A | FAIL |
|
|
|
12/07/98 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Framing/Rough-in | 10/9/1998 | 10/13/1998 | 10/13/1998 | A | FAIL |
Tom Arcoraci
|
|
|
10/13/98 408 - DAN ###-####
|
INSP - Concrete | 9/17/1998 | 9/18/1998 | 9/18/1998 | A | PASS |
Tom Arcoraci
|
|
|
09/18/98 408 - DAN ###-#### GROUT POUR OK
|
INSP - Concrete | 9/15/1998 | 9/16/1998 | 9/17/1998 | P | PASS |
Tom Arcoraci
|
|
|
09/16/98 408 - dan ###-#### concrete block insp.
|
INSP - Foundation | 9/3/1998 | 9/4/1998 | 9/4/1998 | A | PASS |
Tom Arcoraci
|
|
|
09/04/98 408 - slab dan ###-####
|
INSP - Foundation | 8/20/1998 | 8/21/1998 | 8/21/1998 | A | PASS |
Tom Arcoraci
|
|
|
08/21/98 408 - dan ###-####
|
INSP - Foundation | 8/17/1998 | 8/18/1998 | 8/18/1998 | P | PART |
Tom Arcoraci
|
|
|
08/18/98 408 - DAN ###-#### FOOTINGS ALMOST COMPLETE
|