INSP - Final | 8/13/1999 | 8/16/1999 | 8/16/1999 | P | PASS |
|
|
|
08/16/99 338 - made ok for finall/c issued # 16436
|
INSP-Final Inspection | 8/13/1999 | 8/16/1999 | 8/16/1999 | A | PASS |
Rick Jackson
|
|
|
DAN ###-#### (BOISE HIGH #-THEY WILL PAGE DAN) occupancy approved
|
INSP - Final | 8/4/1999 | 8/5/1999 | 8/5/1999 | A | FAIL |
|
|
|
x-it signage not correct sub basement. doors in the exit path cannot lock c/n issued conference with stubbs
|
INSP-Conference | 8/5/1999 | 8/5/1999 | 8/5/1999 | P | PART |
Rick Jackson
|
|
|
met with Perry about exit signs in sub-basement area; they wern't installed with the architects request
|
INSP-Final Inspection | 8/2/1999 | 8/2/1999 | 8/2/1999 | P | FAIL |
Rick Jackson
|
|
|
exit signs still installed in wrong locations in sub-basement area
|
INSP-Conference | 7/22/1999 | 7/22/1999 | 7/22/1999 | P | PART |
Rick Jackson
|
|
|
discussed with architect location of exit signs in sub-basement area
|
INSP-Final Inspection | 7/16/1999 | 7/16/1999 | 7/16/1999 | P | FAIL |
Rick Jackson
|
|
|
exit signs
|
INSP-Final Inspection | 7/15/1999 | 7/15/1999 | 7/15/1999 | P | PART |
Rick Jackson
|
|
|
LISA ###-#### sprinkler system all complete
|
INSP-Alarm Testing | 6/28/1999 | 6/28/1999 | 6/28/1999 | | FAIL |
Rick Jackson
|
|
|
/ / 409 - ALARMS COMPLETE EXCEPT FOR AHU DETECTORS FOR SHUTDOWM; FIRE
|
INSP - Framing/Rough-in | 5/25/1999 | 5/25/1999 | 5/25/1999 | P | PART |
|
|
|
05/25/99 338 - ok for east wing border tiles to be dropped clouds need w
|
INSP - Framing/Rough-in | 4/26/1999 | 4/26/1999 | 4/27/1999 | P | PART |
|
|
|
04/26/99 338 - madeok for the shaft
|
INSP - Framing/Rough-in | 4/22/1999 | 4/23/1999 | 4/23/1999 | A | PART |
|
|
|
04/23/99 338 - made ok to cover the shaft
|
INSP - Framing/Rough-in | 4/14/1999 | 4/14/1999 | 4/15/1999 | P | PART |
|
|
|
04/14/99 338 - madeok to cover at the east wing
|
INSP - Framing/Rough-in | 3/31/1999 | 4/2/1999 | 4/5/1999 | A | PART |
|
|
|
04/02/99 338 - made ok for the west wing
|
INSP-Final Inspection | 3/26/1999 | 3/26/1999 | 3/26/1999 | P | PART |
Rick Jackson
|
|
|
temp occ approved for limited areas; exiting okay
|
INSP-Alarm Testing | 3/22/1999 | 3/22/1999 | 3/22/1999 | A | PART |
Rick Jackson
|
|
|
tested elevator and recall -okay; alarm panels are networked and appear to work as main building has dialer and can silence from there. devices are "main" or "I/A" building
|
INSP-Alarm Testing | 3/18/1999 | 3/18/1999 | 3/18/1999 | P | NR |
Rick Jackson
|
|
|
not ready for elevator, networking - rescheduled for 3/22
|
INSP-Conference | 3/16/1999 | 3/16/1999 | 3/16/1999 | A | PART |
Rick Jackson
|
|
|
standpipes to remain connected until fully sprinklered; informed jim Stubbs of alarm requirements for network
|
INSP - Framing/Rough-in | 2/26/1999 | 3/1/1999 | 3/2/1999 | A | PART |
|
|
|
03/01/99 338 - NOT READY FOR OK TO DROP IN TILES
|
INSP-Conference | 2/18/1999 | 2/18/1999 | 2/18/1999 | P | PART |
Rick Jackson
|
|
|
requirements for occupying completed areas until project is completed
|
INSP - Framing/Rough-in | 2/8/1999 | 2/9/1999 | 2/9/1999 | A | PART |
|
|
|
###-#### JIM rescheduled for 7:00 02/10/99
|
INSP - Framing/Rough-in | 2/4/1999 | 2/5/1999 | 2/5/1999 | A | FAIL |
|
|
|
02/05/99 338 - ###-#### jim\ceiling grid no answer in the contact # no r
|
INSP-Sprinkler Rough-in/Hydro | 2/2/1999 | 2/2/1999 | 2/2/1999 | | FAIL |
Rick Jackson
|
|
|
/ / 409 - EXPOSED COMBUSTIBLES NOT SPRINKLERED OR COVERED
|
INSP-Conference | 11/23/1998 | 11/24/1998 | 11/24/1998 | A | PART |
Rick Jackson
|
|
|
with architect and general to determine sprinklering or covering combustibles above dropped ceiling - they will cover
|
INSP-Sprinkler Rough-in/Hydro | 11/23/1998 | 11/23/1998 | 11/23/1998 | A | FAIL |
Rick Jackson
|
|
|
basement and first floor only c/n to be issued
|
INSP-Sprinkler Rough-in/Hydro | 11/16/1998 | 11/16/1998 | 11/16/1998 | P | FAIL |
Rick Jackson
|
|
|
checked sprinkler piping in basement - numerous problems. requested shilo to clean up areas and they requested us back to re-inspect on 11/20
|
INSP-Supply line flush | 11/13/1998 | 11/13/1998 | 11/13/1998 | A | PASS |
Rick Jackson
|
|
|
underground flush okay - new PIV installed needs hydro
|
INSP - Framing/Rough-in | 11/4/1998 | 11/5/1998 | 11/5/1998 | P | PART |
Wes Worcester
|
|
|
11/05/98 342 - JIM ###-####- SMOKE CEILING AROUND PIPES-CHECK CHASES
|
INSP - Framing/Rough-in | 10/23/1998 | 10/23/1998 | 10/23/1998 | P | PART |
|
|
|
10/23/98 333 - basement ceiling and second fl frame ok
|
INSP-Sprinkler Rough-in/Hydro | 10/5/1998 | 10/5/1998 | 10/5/1998 | P | PART |
Rick Jackson
|
|
|
sprinklers not needed under south canopy (awaiting letter from school about keeping combustibles from under canopy); sway bracing needed in basement; heads overspaced in basement bathroom
|
INSP - Framing/Rough-in | 9/22/1998 | 9/23/1998 | 9/23/1998 | P | PART |
|
|
|
09/23/98 333 - basement ok
|
INSP-Sprinkler Rough-in/Hydro | 9/11/1998 | 9/11/1998 | 9/11/1998 | A | FAIL |
Rick Jackson
|
|
|
sprinkler system designed for over 100 psi - hangers not within 12 inches from end of pipe. obstructed heads in basement. c/n issued
|
INSP - Framing/Rough-in | 9/1/1998 | 9/1/1998 | 9/1/1998 | | PART |
|
|
|
09/01/98 333 - grid in baths ok
|
INSP - Framing/Rough-in | 8/31/1998 | 9/1/1998 | 9/1/1998 | A | PART |
|
|
|
09/01/98 333 - bath grid ok
|
INSP - Framing/Rough-in | 8/6/1998 | 8/6/1998 | 8/6/1998 | P | PART |
|
|
|
08/06/98 333 - south wing ok
|
INSP - Framing/Rough-in | 7/30/1998 | 7/31/1998 | 7/31/1998 | A | PART |
|
|
|
07/31/98 333 - bath ok
|
INSP - Framing/Rough-in | 7/24/1998 | 7/27/1998 | 7/27/1998 | A | PART |
|
|
|
07/27/98 333 - east bathrooms ok to cover
|
INSP - Final | 7/23/1998 | 7/24/1998 | 7/24/1998 | A | NR |
Jim Storey
|
|
|
07/24/98 301 - JIM STUBBS ###-#### ok to cover bathroom common plumbing floor
|
INSP - Framing/Rough-in | 7/15/1998 | 7/16/1998 | 7/16/1998 | A | PART |
|
|
|
07/16/98 333 - first floor
|
INSP - Framing/Rough-in | 7/1/1998 | 7/2/1998 | 7/2/1998 | A | PART |
|
|
|
07/02/98 333 - ceiling in east half of south wing ok
|
INSP - Framing/Rough-in | 6/29/1998 | 6/29/1998 | 6/29/1998 | P | PART |
|
|
|
06/29/98 333 - corridor wall ok
|
INSP - Framing/Rough-in | 6/26/1998 | 6/26/1998 | 6/26/1998 | P | PASS |
|
|
|
06/26/98 333 - south east side of corridor ok
|
INSP - Framing/Rough-in | 6/17/1998 | 6/17/1998 | 6/17/1998 | P | PASS |
|
|
|
06/17/98 333 - EAST SIDE OF SOUTH WING OFFICES
|
INSP - Foundation | 6/12/1998 | 6/15/1998 | 6/15/1998 | A | PASS |
|
|
|
06/15/98 333 - FTG -OK FOOTING
|
INSP - Foundation | 6/10/1998 | 6/10/1998 | 6/10/1998 | A | PART |
|
|
|
06/10/98 333 - in progress
|