INSP - Final | 11/10/1998 | 11/10/1998 | 11/10/1998 | P | PASS |
Carl Dependahl
|
|
|
JACK BARBER ###-#### FN OCC INSP l/c issued
|
INSP - Foundation | 11/6/1998 | 11/6/1998 | 11/6/1998 | A | PASS |
Carl Dependahl
|
|
|
incomplete entry w/ earlier insp.
|
INSP - Framing/Rough-in | 10/13/1998 | 10/13/1998 | 10/13/1998 | A | PASS |
Carl Dependahl
|
|
|
c/n ok, truss fix ok. ok to complete cover.
|
INSP - Energy code compliance | 10/9/1998 | 10/9/1998 | 10/9/1998 | P | PASS |
Carl Dependahl
|
|
|
reinsp.
|
INSP - Framing/Rough-in | 10/7/1998 | 10/7/1998 | 10/7/1998 | P | PART |
Carl Dependahl
|
|
|
truss eng's fix...eng'r located add'l build problem w/ truss t-1; & gable end truss; ok to cover except as noted, add'l letter to follow.
|
INSP - Framing/Rough-in | 10/6/1998 | 10/6/1998 | 10/6/1998 | P | PART |
Carl Dependahl
|
|
|
jack ###-####; need stamped eng'g for trusses, however, proposed fix onsite....ok to cover common wall.
|
INSP - Framing/Rough-in | 10/5/1998 | 10/5/1998 | 10/5/1998 | P | FAIL |
Carl Dependahl
|
|
|
meet w/ truss eng...ENG TO SUBMIT "FIXES" OR ALTERNATES FOR IMPROPER INSTALL & MISSED BRG...TRUSSES REVERSED. KEEP C/N
|
INSP - Energy code compliance | 9/25/1998 | 9/25/1998 | 9/25/1998 | | PART |
Carl Dependahl
|
|
|
from wes?? ok to insul and cover common 1hr walls only
|
INSP - Framing/Rough-in | 9/25/1998 | 9/25/1998 | 9/25/1998 | P | FAIL |
Carl Dependahl
|
|
|
tom ###-####...need truss designer to examine and approve trusses, bearing points missed, lumber not per eng'g spec on at least one truss member...also, seal/firestop penetrations at 1hr wall.make elec. c/n. ok to insulate & cover common walls only.
|
INSP - Framing/Rough-in | 9/22/1998 | 9/22/1998 | 9/22/1998 | | PART |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ok to insuate
|
INSP - Framing/Rough-in | 9/21/1998 | 9/21/1998 | 9/21/1998 | A | NR |
Carl Dependahl
|
|
|
conf only; ok to use "Borup" exc...delete attic 1hr "draft stop"
|
INSP - Framing/Rough-in | 9/1/1998 | 9/1/1998 | 9/1/1998 | P | NR |
Carl Dependahl
|
|
|
conf w/ Mike Phillips re plan review req's/ plan originally done by Dick Pierce.
|
INSP - Framing/Rough-in | 8/31/1998 | 8/31/1998 | 8/31/1998 | P | NR |
Carl Dependahl
|
|
|
conf only.1hr walls
|
INSP - Foundation | 7/22/1998 | 7/22/1998 | 7/22/1998 | P | PASS |
Carl Dependahl
|
|
|
07/22/98 340 - FOOTINGS JACK ###-####
|