Permit NumberBLD98-01188
StatusExpired
Name REDHAWK COURT
Site Address 9280 W BARNES DR
Project NameRED HAWK COURT
Customer Number 
ePlanReviewNo
Description
RED HAWK COURT (SHELL BUILDING) - TO CONSTRUCT A NEW 13,820 SQ. FT., ONE STORY OFFICE SHELL BUILDING. TO BE CONSTRUCTED OF WOOD FRAMED EXTERIOR WALLS, STEEL INTERIOR STRUCTURAL COLUMNS SUPPORTING GLU-LAM BEAMS, TRUSS JOIST ROOF TRUSSES, SINGLE PLY ROOFING SYSTEM AND CONCRETE SLAB FLOORS. tHIS BUILDING TO BE FULLY FIRE SPRINKLED. THIS PERMIT ALSO INCLUDES RELATED SITE IMPROVEMENTS. THIS PERMIT IS FOR THE CONSTRUCTION OF A SHELL BUILDING ONLY, NO OCCUPANCY WILL BE ALLOWED UNDER THIS PERMIT. SEPARATE TENANT IMPROVEMENT PERMITS WILL BE REQUIRED TO FINISH EACH TENANT OFFICE SPACE. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. DR98-0022/PC#266-98/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final6/10/19996/10/19996/10/1999 PASS
DetailsCarl Dependahl
/ / 340 - LC 17600 ISSUED
INSP - Final6/8/19996/9/19996/9/1999APASS
DetailsCarl Dependahl
06/09/99 340 - ###-####//FINALok, l/c issued at site. will bring card in
INSP - Final6/8/19996/8/19996/8/1999 NH
DetailsCarl Dependahl
06/08/99 340 - Scheduled by Hello!. Contact phone is [8692072].
INSP - Final5/18/19995/18/19995/18/1999 FAIL
DetailsWes Worcester
05/18/99 342 - Scheduled by Hello!. Contact phone is [8692072].
INSP-Final Inspection3/16/19993/17/19993/17/1999APASS
DetailsJoe Tawney
03/17/99 406 - REINSP OK FOR CERT OF COMPLETION ON SHELL
INSP-Final Inspection2/25/19992/26/19992/26/1999AFAIL
Details
Scheduled by Hello!. Contact phone is [8692072]. no alarm plans provided, alarm panel not correct for sprinkler supervisory. Fire Riser room not protected w/ 1 hr construction.
INSP-Sprinkler Rough-in/Hydro2/18/19992/18/19992/18/1999 PART
DetailsJoe Tawney
/ / 406 - OK ON ABOVE AND UNDERGROUND HYDRO TESTS
INSP-Supply line flush2/17/19992/17/19992/17/1999 PART
DetailsJoe Tawney
/ / 406 - OK ON SUPPLY LINE FLUSH
INSP - Framing/Rough-in11/17/199811/18/199811/19/1998PPART
Details
11/19/98 338 - made ok for the ext wall insulation and efis to be instal
INSP - Framing/Rough-in11/18/199811/18/199811/18/1998 PART
Details
11/18/98 338 - made ok for cover ext of ext walls and
INSP - Foundation9/23/19989/24/19989/24/1998APART
Details
09/24/98 338 - made ok r-bar placed for rest of footings and the first s
INSP - Foundation9/17/19989/18/19989/18/1998APART
Details
09/17/98 338 - MADE OK TO POUR R-BAR IS PLACED BULKHEADS IN PLACE. NORTH