INSP-Final Inspection | 6/10/1999 | 6/10/1999 | 6/10/1999 | P | PASS |
Joe Tawney
|
|
|
06/10/99 406 - REINSP EL DOORS OK OK FOR CERT OF COMPLETION
|
INSP - Final | 6/1/1999 | 6/1/1999 | 6/1/1999 | P | PASS |
|
|
|
06/01/99 338 - madeok for l/c
|
INSP - Final | 3/26/1999 | 3/29/1999 | 3/31/1999 | A | PASS |
|
|
|
03/29/99 338 - madeok other agencies approved
|
INSP-Final Inspection | 3/26/1999 | 3/26/1999 | 3/26/1999 | P | FAIL |
Rick Jackson
|
|
|
###-#### kerry door rating not correct tag
|
INSP-Conference | 3/9/1999 | 3/9/1999 | 3/9/1999 | P | PART |
Rick Jackson
|
|
|
told Ivan (total door installer) to get appropriate label on the elevator door - he will call when ready for re-inspection
|
INSP-Conference | 2/8/1999 | 2/8/1999 | 2/8/1999 | A | PART |
Rick Jackson
|
|
|
informed contractor that the total doors for the elevators require 1 hr protection as shown on plans
|
INSP - Final | 2/4/1999 | 2/5/1999 | 2/8/1999 | P | FAIL |
|
|
|
02/05/99 338 - naad to ok with fire insp as the total doors are not poer
|
INSP-Final Inspection | 2/4/1999 | 2/5/1999 | 2/5/1999 | P | FAIL |
Rick Jackson
|
|
|
02/05/99 409 - KERRY ###-#### elevator doors not rated to 1 hr per plans; exit sign at 2nd floor fire
|
INSP - Final | 1/8/1999 | 1/11/1999 | 1/11/1999 | A | FAIL |
|
|
|
01/11/99 338 - other agencies not approved
|
INSP - Framing/Rough-in | 9/22/1998 | 9/22/1998 | 9/22/1998 | P | PASS |
|
|
|
09/22/98 333 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 9/3/1998 | 9/3/1998 | 9/3/1998 | P | PASS |
|
|
|
09/03/98 333 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 8/31/1998 | 8/31/1998 | 8/31/1998 | P | PART |
|
|
|
08/31/98 333 - south stairs okj
|