INSP - Final | 11/6/1998 | 11/6/1998 | 11/6/1998 | A | PASS |
Tom Arcoraci
|
|
|
|
INSP - Final | 11/4/1998 | 11/4/1998 | 11/5/1998 | P | FAIL |
Tom Arcoraci
|
|
|
11/04/98 408 - JOHN ###-#### ok for letter of comp after electric final
|
INSP - Final | 10/28/1998 | 10/28/1998 | 10/28/1998 | | NR |
|
|
|
10/28/98 338 - JOHN ###-#### FN INSP need other agencies smoke detectors
|
INSP - Final | 10/22/1998 | 10/23/1998 | 10/23/1998 | A | CANC |
|
|
|
10/23/98 338 - cancelled by the conter john
|
INSP - Framing/Rough-in | 8/12/1998 | 8/13/1998 | 8/14/1998 | P | PASS |
|
|
|
08/13/98 338 - john ###-####
|
INSP - Framing/Rough-in | 8/7/1998 | 8/10/1998 | 8/10/1998 | P | PART |
|
|
|
08/10/98 338 - made ok to insulate minor strapping hangers and nailing n
|
INSP - Foundation | 6/16/1998 | 6/17/1998 | 6/19/1998 | A | PASS |
|
|
|
06/18/98 338 - made ok
|
INSP - Foundation | 6/16/1998 | 6/16/1998 | 6/16/1998 | P | NR |
|
|
|
06/16/98 338 - NOT READY CALLED TO CANCELL TILL TOMORROW
|
INSP - Foundation | 6/15/1998 | 6/16/1998 | 6/16/1998 | A | PASS |
|
|
|
06/16/98 338 - MADE OK FOR THE FOOTING ONLY MUST INSPECT THE FOUNDATION
|
INSP - Foundation | 6/15/1998 | 6/15/1998 | 6/15/1998 | P | NR |
|
|
|
06/15/98 338 - not ready no forms set still gutting out the interior
|