INSP - Framing/Rough-in | 11/9/1998 | 11/9/1998 | 11/9/1998 | P | FAIL |
|
|
|
11/09/98 333 - CN NOT MADE MECH NOT DONE
|
INSP - Framing/Rough-in | 11/6/1998 | 11/6/1998 | 11/6/1998 | P | FAIL |
Carl Dependahl
|
|
|
rec'd resubmittal for additional attic room space/reconfiguration...need info for fllor framing, verify rafters/spacing, etc. keep c/n....will consult Kim as to previous insp's.
|
INSP - Framing/Rough-in | 11/5/1998 | 11/5/1998 | 11/5/1998 | A | FAIL |
Carl Dependahl
|
|
|
333 area; keep c/n...conf only w/ bldr & architect, need resubmittal for changes at attic. ok to insulate only.
|
INSP - Framing/Rough-in | 11/3/1998 | 11/4/1998 | 11/4/1998 | A | FAIL |
Carl Dependahl
|
|
|
###-#### FRAMING
|
INSP - Framing/Rough-in | 10/30/1998 | 11/2/1998 | 11/2/1998 | A | FAIL |
|
|
|
11/02/98 333 - elec not done
|
INSP - Foundation | 9/23/1998 | 9/23/1998 | 9/23/1998 | P | PART |
|
|
|
09/23/98 333 - talked about shear and headers
|
INSP - Foundation | 9/1/1998 | 9/2/1998 | 9/2/1998 | P | PASS |
|
|
|
09/02/98 333 - FDN -OK FOUNDATION
|
INSP - Foundation | 8/28/1998 | 8/31/1998 | 8/31/1998 | P | CANC |
|
|
|
08/31/98 333 - canc by contractor
|