Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD98-02277
StatusFinaled
Name TODD MASSEY
Site Address 5115 W STATE ST
Project NameECONO-LUBE N TUNE
Customer Number 
ePlanReviewNo
Description
ECONO-LUBE N'TUNE * TO CONSTRUCT A 2,561 SQ. FT. AUTOMOTIVE LUBRICATION AND REPAIR BUILDING INCLUDING SITE DEVELOPMENT. THE BUILDING IS SLAB ON GRADE WITH A REPAIR PIT CMU WALLS AND TJI ROOF. DRH98-56 PC#516-98 JML NOTE: ACHD NEED TO BE VERIFIED.MPS
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final5/7/19995/10/19995/10/1999APASS
DetailsWes Worcester
05/10/99 342 - Jerry ###-####
INSP-Final Inspection5/7/19995/10/19995/10/1999APASS
DetailsJoe Tawney
05/10/99 406 - REINSP OK FOR PERM OCC
Permanent Occupancy 5/10/19995/10/1999 DONE
Details
INSP-Final Inspection5/7/19995/7/19995/7/1999PFAIL
DetailsJoe Tawney
05/07/99 406 - FINAL FAIL DOOR HDWRE, RR SIGN
INSP-Final Inspection5/6/19995/6/19995/7/1999PFAIL
DetailsWes Worcester
05/06/99 342 - need fire inspection
INSP - Final5/6/19995/6/19995/6/1999PFAIL
DetailsCarl Dependahl
05/06/99 340 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Wall cover4/12/19994/12/19994/12/1999 PART
DetailsCarl Dependahl
/ / 340 - CONF ONLY, REFERRED TO PUB WKS.
INSP - Framing/Rough-in4/5/19994/5/19994/5/1999 PART
DetailsCarl Dependahl
/ / 340 - CONF ONLY W/ JERRY, SUPT RE FINALS
INSP - Framing/Rough-in3/30/19993/30/19993/30/1999PPASS
DetailsWes Worcester
03/30/99 342 - ###-#### gerry econo lube
INSP - Framing/Rough-in3/17/19993/17/19993/17/1999PPART
DetailsCarl Dependahl
03/17/99 340 - jerry ###-#### deck nailing ispection 342 area, roof deck & wall ties ok to cover
INSP - Framing/Rough-in3/16/19993/17/19993/17/1999AFAIL
DetailsWes Worcester
03/17/99 342 - ROOF DECK NAILING JERRY ###-#### no one on site
INSP - Framing/Rough-in2/24/19992/25/19992/25/1999APART
DetailsCarl Dependahl
02/25/99 340 - grouting masonry, pend spec insp report.
INSP - Framing/Rough-in1/20/19991/21/19991/21/1999APART
DetailsCarl Dependahl
01/21/99 340 - JERRY ###-#### WILL POUR AT 10:00. witnessed spec ins bar in place, weld test to be done for nw corner lintel, etc. pending re
INSP - Foundation1/14/19991/14/19991/14/1999 PART
DetailsCarl Dependahl
/ / 340 - fnd walls, pending spec insp report. looks ok.
INSP - Foundation1/11/19991/12/19991/12/1999PPART
DetailsCarl Dependahl
01/12/99 340 - POURING AT 1:00---JERRY ###-####...part, ext ftgs,pen
INSP - Concrete1/4/19991/4/19991/4/1999APART
DetailsCarl Dependahl
conf only; requested spec insp reports, supt. will follow up.
INSP - Concrete12/30/199812/30/199812/30/1998PPART
DetailsCarl Dependahl
membrane at pit floor; bituthene installed
INSP - Concrete12/17/199812/17/199812/17/1998PPART
DetailsCarl Dependahl
"pit" walls...pending spec insp report.
INSP - Foundation12/15/199812/15/199812/15/1998PPART
DetailsCarl Dependahl
pending spec insp report.
INSP - Framing/Rough-in12/11/199812/14/199812/14/1998AFAIL
DetailsCarl Dependahl
gerry ###-#### cell -walls insp-ordered slump test not frame insp....no plans onsite...left card
INSP - Concrete12/8/199812/8/199812/8/1998PFAIL
DetailsCarl Dependahl
supt. not onsite...ftgs pending spec insp reports.
INSP - Foundation11/30/199812/1/199812/1/1998APART
DetailsRuss Owen
12/01/98 407 - FOOTING AT SLAB FOR LUBE PIT. CONTRACTOR TO PLACE VERTICA
INSP - Foundation12/1/199812/1/199812/1/1998PPART
DetailsCarl Dependahl
econo lube; pending spec insp reports, told concrete contractor to have city plans onsite for insp's
INSP - Foundation11/30/199811/30/199811/30/1998PCANC
DetailsCarl Dependahl
WILL RESCHEDULE
INSP - Concrete11/23/199811/23/199811/23/1998PPART
DetailsCarl Dependahl
JERRY WIGGINS 3:00 PM ###-#### ECONO LUBE; PRE-CON CONF. pre-con conference; requested spec inspection/compaction reports...explained insp. process, etc. Not ready to pour