INSP - Letter of compliance | 1/26/1999 | 1/26/1999 | 1/26/1999 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - lc11493
|
INSP - Letter of compliance | 1/26/1999 | 1/26/1999 | 1/26/1999 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - lc11493
|
INSP - Final | 1/25/1999 | 1/25/1999 | 1/25/1999 | P | PASS |
Carl Dependahl
|
|
|
/ / 340 - larry ###-#### fn occ insp
|
INSP - Final | 12/16/1998 | 12/17/1998 | 12/17/1998 | P | FAIL |
Jim Sly
|
|
|
12/17/98 316 - No access and Not ready...
|
INSP - Framing/Rough-in | 10/28/1998 | 10/28/1998 | 11/17/1998 | A | PASS |
Jim Sly
|
|
|
11/17/98 316 - LARRY ###-####
|
INSP - Framing/Rough-in | 10/29/1998 | 10/29/1998 | 10/29/1998 | A | PASS |
Carl Dependahl
|
|
|
316 area,
|
INSP - Framing/Rough-in | 10/28/1998 | 10/28/1998 | 10/28/1998 | P | PASS |
Carl Dependahl
|
|
|
316 area took for sly;reinsp ok
|
INSP - Framing/Rough-in | 10/26/1998 | 10/27/1998 | 10/27/1998 | A | FAIL |
Jim Sly
|
|
|
10/27/98 316 - C/N...2x6 or 3x4 studs at pony carry 2 flrs and roof.
|
INSP - Framing/Rough-in | 10/5/1998 | 10/6/1998 | 10/6/1998 | A | PART |
Jim Sly
|
|
|
10/06/98 316 - Shear wall OK....
|
INSP - Foundation | 8/17/1998 | 8/18/1998 | 8/18/1998 | A | NR |
Tom Arcoraci
|
|
|
08/18/98 408 - NO At ###-#### 14236 footing NO APPROVED PLANS APPEARS OK
|
INSP - Foundation | 8/13/1998 | 8/13/1998 | 8/13/1998 | P | FAIL |
Jim Sly
|
|
|
08/13/98 316 - Footing poured W/O insp...No appr plans...
|
INSP - Foundation | 8/12/1998 | 8/12/1998 | 8/12/1998 | P | NR |
Jim Sly
|
|
|
08/12/98 316 - NR...4:30 PM....
|