Permanent Occupancy | | 6/4/1999 | 6/4/1999 | | DONE |
|
|
|
|
INSP - Final | 10/29/1998 | 10/29/1998 | 10/30/1998 | P | PASS |
|
|
|
10/29/98 338 - made ok signed the perm col of occ req card
|
INSP - Final | 10/29/1998 | 10/29/1998 | 10/29/1998 | | NH |
|
|
|
/ / 338 - DOOR LOCKED BY MISTAKE IF BUILDER WILL REQUEST , CAN RE-INSP
|
INSP-Final Inspection | 10/28/1998 | 10/28/1998 | 10/28/1998 | P | PASS |
Joe Tawney
|
|
|
10/28/98 406 - RAY ###-#### FINAL OK FOR PERM OCC
|
INSP - Framing/Rough-in | 9/30/1998 | 10/1/1998 | 10/1/1998 | P | PASS |
Tom Arcoraci
|
|
|
10/01/98 408 - RAY ###-#### -FR-IN INSP
|
INSP - Conference | 9/30/1998 | 9/30/1998 | 9/30/1998 | | PART |
|
|
|
/ / 338 - CONTRACTOR ,S HELPER LOCKED THE DOOR WILL RESCHEDULE FRAMING
|
INSP - Conference | 9/30/1998 | 9/30/1998 | 9/30/1998 | | PART |
|
|
|
/ / 338 - CONTRACTOR ,S HELPER LOCKED THE DOOR WILL RESCHEDULE FRAMING
|