INSP - Final | 3/2/1999 | 3/2/1999 | 3/2/1999 | P | PASS |
Wes Worcester
|
|
|
03/02/99 342 - mike ###-####
|
INSP - Grading Inspection | 3/2/1999 | | 3/2/1999 | | BOND |
Rita DeYoung
|
|
|
Rough grading complete. Fine grading, revegetation, and restoration of the adjoining lot to the south are yet to be completed. Engineer has recommended a $700.00 surety. Upon receipt of this surety the grading is conditionally approved by Public Works.
|
INSP - Energy code compliance | 12/18/1998 | 12/18/1998 | 12/18/1998 | P | PASS |
Wes Worcester
|
|
|
12/18/98 342 - mike- ###-#### energy code-to cover
|
INSP - Framing/Rough-in | 12/16/1998 | 12/17/1998 | 12/17/1998 | A | PASS |
Wes Worcester
|
|
|
12/17/98 342 - MIKE...###-####
|
INSP - Framing/Rough-in | 12/2/1998 | 12/3/1998 | 12/3/1998 | A | FAIL |
Wes Worcester
|
|
|
12/03/98 342 - ADD TWO STRAPS, NAIL PER PLAN AND STAPLE 6/12 AT EACH END
|
INSP - Foundation | 10/13/1998 | 10/14/1998 | 10/14/1998 | P | PASS |
Wes Worcester
|
|
|
10/14/98 342 - Scheduled by Hello!. Contact phone is [8675068].
|
INSP - Foundation | 10/5/1998 | 10/6/1998 | 10/6/1998 | A | PART |
Wes Worcester
|
|
|
10/06/98 342 - ROBERT ###-####
|