INSP - Final | 9/22/1998 | 9/22/1998 | 9/22/1998 | P | PASS |
|
|
|
09/22/98 338 -
|
INSP - Final | 9/21/1998 | 9/21/1998 | 9/21/1998 | | NR |
|
|
|
/ / 338 - OWNER CALLED TOO MOVE INSPECTION TO NEXT DAY AFTER THE PLMG
|
INSP - Final | 9/21/1998 | 9/21/1998 | 9/21/1998 | P | NR |
|
|
|
other agencies not approved plmg c/n for back flow registration and shut off valve for same
|
INSP - Final | 9/17/1998 | 9/17/1998 | 9/17/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - FINAL OK FOR CERT OF COMPLETION
|
INSP - Wall cover | 9/15/1998 | 9/16/1998 | 9/16/1998 | A | NR |
|
|
|
09/17/98 338 - robert ###-#### suspended ceiling this inspection is to b
|
INSP - Framing/Rough-in | 8/24/1998 | 8/25/1998 | 8/25/1998 | A | PART |
|
|
|
08/25/98 338 - ok to cover all with the other agencies blessing the work
|
INSP - Framing/Rough-in | 8/21/1998 | 8/21/1998 | 8/20/1998 | A | PART |
|
|
|
08/21/98 338 - robert ###-#### made ok with micro-lam lledger on the sou
|