Permit Information
Permit NumberBLD98-02647
StatusFinaled
Name SEIDL HOME CO INC
Site Address 521 E SUNNYRIDGE CT
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 3385 sq. ft. two story single family dwelling with a 776 sq. ft. attached three car garage, two lighweight concrete 2nd level balconies (one covered), and free-form concrete patio per approved plans, all attached engineering and requirement lists and all red-lining. (1st floor 1420 sq. ft.) (2nd floor 1965 sq. ft.) This lot is located within a hillside area and is subject to the hillside ordinance. Class "A" roof system will be required. CU #37-91 PC #804 DJO
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final8/17/19998/18/19998/20/1999APASS
DetailsWes Worcester
08/18/99 342 - 08/17/99 342 - jon ###-#### fn occ inp
INSP - Grading Inspection8/19/1999 8/19/1999 PASS
DetailsRita DeYoung
FINAL GRADING APPROVED
INSP - Final8/16/19998/17/19998/17/1999PFAIL
DetailsWes Worcester
08/17/99 342 - JOHN ###-#### NEED MECHANICAL
INSP - Framing/Rough-in4/27/19994/27/19994/27/1999PPART
DetailsWes Worcester
04/27/99 342 - ###-#### ERIC//FRAMING REINSPECTION Russ signed off
INSP - Framing/Rough-in4/23/19994/26/19994/27/1999APASS
DetailsRuss Owen
04/26/99 407 - framing reinspect/ Eric ###-####
INSP - Framing/Rough-in4/22/19994/23/19994/23/1999AFAIL
DetailsRuss Owen
04/23/99 407 - still has correction posted,not done re-inspect required.
INSP - Energy code compliance4/22/19994/23/19994/22/1999APASS
DetailsRuss Owen
04/23/99 407 - Eric ###-####
INSP - Energy code compliance4/21/19994/22/19994/22/1999APASS
DetailsRuss Owen
04/22/99 407 - John ###-####
INSP - Framing/Rough-in4/21/19994/22/19994/22/1999AFAIL
DetailsRuss Owen
04/22/99 407 - John ###-####
INSP - Framing/Rough-in4/19/19994/20/19994/20/1999AFAIL
DetailsRuss Owen
04/20/99 407 - ok from special inspection on hold downs,also has correti
INSP - Foundation4/16/19994/16/19994/16/1999PFAIL
DetailsWes Worcester
04/16/99 342 - shear late pm\\###-####
INSP - Framing/Rough-in4/12/19994/12/19994/11/1999PFAIL
DetailsWes Worcester
04/12/99 342 - sheer wall Eric ###-#### no one on site to witness, eng
INSP - Framing/Rough-in4/8/19994/8/19994/8/1999 FAIL
DetailsWes Worcester
04/08/99 342 - Sheer inspection call Eric first ###-####
INSP - Framing/Rough-in4/7/19994/8/19994/8/1999AFAIL
DetailsWes Worcester
04/08/99 342 - Sheer inspection call Eric first ###-#### all thread bolt
INSP - Framing/Rough-in3/24/19993/25/19993/25/1999AFAIL
DetailsWes Worcester
03/25/99 342 - ###-#### john not even close, Russ finished inspection
INSP - Wall cover3/25/19993/25/19993/25/1999 FAIL
DetailsRuss Owen
/ / 407 - ENGINEERED ITEMS NOT DONE.DO NOT COVER.
INSP - Foundation11/30/199811/30/199811/30/1998PPASS
DetailsWes Worcester
11/30/98 342 - JOHN ###-#### FT INSP
INSP - Foundation11/25/199811/27/199811/27/1998APART
DetailsWes Worcester
11/27/98 342 - JOHN ###-#### ì