Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD98-02988
StatusFinaled
Name FOREST RIVER OFFICE/RESTAURANT
Site Address 913 W RIVER ST
Project NameFOREST RIVER
Customer Number 
ePlanReviewNo
Description
FOREST RIVER OFFICE/RESTAURANT (SHELL & CORE)* TO CONSTRUCT A NEW 55,895 SQ. FT., FOUR STORY OFFICE AND RESTAURANT SHELL AND CORE BUILDING AND RELATED SITE IMPROVEMENTS. CONSTRUCTED OF STEEL STRUCTURAL FRAME, METAL PAN AND CONCRETE FLOOR SYSTEMS, METAL ROOF DECK AND METAL AND MASONRY WALL CONSTRUCTION. THIS BUILDING IS FULLY FIRE SPRINKLED. THE SPRINKLERS ARE BEING USED FOR ONE-HOUR FIRE-RESISTIVE SUBSTITUTION. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. PC3678-98/DRH98-0109/CUP98-0071/JCM GRADING PERMIT UNDER BLD98-2320 FOUNDATION PERMIT UNDER BLD98-2299
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/3/199912/3/199912/3/1999PPASS
Details
JAY ###-#### L/C issued #18289
BLD-Conference12/1/199912/1/199912/1/1999 PASS
Talked w/Marv Meyer & Leonard re: status of temp. occ.
BLD-Final9/28/19999/29/19999/30/1999PFAIL
Details
L:eonard ###-#### Ok for temp. occ. For shell only
FIRE-Final Inspection9/28/19999/29/19999/29/1999PFAIL
DetailsRick Jackson
Leonard Butler ###-#### Need UL listing info for smoke guard doors
FIRE-Final Inspection9/22/19999/28/19999/28/1999AFAIL
DetailsRick Jackson
###-#### Test elevator recall/smoke guard; Stair tower door closures; Sprinkler problems; Penetrations in rated ceiling
BLD-Other9/24/19999/24/19999/24/1999APART
Details
recieved notice requesting not to sign occ w/o parks dept ok
BLD-Framing/Rough-in9/23/19999/23/19999/23/1999APART
Details
CEILING GRID INSP.provide suport for main runner in the long hall, perimeter wires , and diffuser attachment required c/n issued
INSP-Final Inspection9/9/19999/10/19999/10/1999PFAIL
DetailsRick Jackson
SPRINKLER HYDRO OK, NOT A FINAL INSPECTION
INSP-Supply line flush9/1/19999/1/19999/1/1999PPASS
DetailsRick Jackson
underground flush okay
INSP - Framing/Rough-in8/26/19998/27/19998/27/1999APART
Details
08/30/99 338 - Jay ###-####
INSP-Conference8/23/19998/23/19998/23/1999APART
Details
on the accessability issue
INSP - Framing/Rough-in8/17/19998/18/19998/18/1999ANR
DetailsJim Storey
08/18/99 301 - 1 HR. ASSEMBLY. JAY ###-####
INSP - Framing/Rough-in8/4/19998/6/19998/5/1999APART
Details
08/06/99 338 - corridor questions
INSP - Framing/Rough-in7/27/19997/27/19997/27/1999PPART
Details
07/27/99 338 - conf on rated corridor walls and for the lobby protection
INSP - Framing/Rough-in7/9/19997/12/19997/12/1999APART
Details
07/12/99 338 - made okkto cover the exterior soffits
INSP - Framing/Rough-in6/22/19996/22/19996/22/1999PPART
Details
06/22/99 338 - ceiling closure Jay --DISCUSSED THE PROPOSED METHOD FOR T
INSP - Wall cover6/11/19996/14/19996/14/1999APART
Details
06/14/99 338 - madeok to cover
INSP - Framing/Rough-in6/4/19996/7/19996/7/1999APART
Details
06/07/99 338 - madeto insuLATE AS NECESSARY AND THE ELEL INSP IS SIGNED
INSP - Framing/Rough-in5/24/19995/25/19995/25/1999PPART
Details
05/25/99 338 - madeok for the cover of the outside of the 2-hour shaft
INSP - Framing/Rough-in5/18/19995/19/19995/19/1999APART
Details
05/19/99 338 - reviewed the framing pending assembly design for the meta
INSP - Framing/Rough-in4/29/19994/29/19994/29/1999P
Details
###-#### JAY//MISC.
INSP - Framing/Rough-in4/26/19994/26/19994/26/1999PPART
Details
04/26/99 338 - OK TO CONTINUE AS IS
INSP-Conference4/22/19994/22/19994/22/1999PPART
DetailsRick Jackson
left c/n for completion of standpipe due by 4/29
INSP - Framing/Rough-in3/24/19993/25/19993/24/1999A
Details
###-#### JAY//FIRE CAULKING IN AIR SHAFT
INSP - Concrete3/16/19993/16/19993/16/1999PPART
DetailsJim Storey
03/16/99 301 - JAY ###-#### STRUCTURAL SLAB 4TH FLOOR AND ROOF work in progess 4 th floor pending special insp. approval and roof ok at
INSP - Framing/Rough-in2/26/19993/1/19993/1/1999APART
Details
03/01/99 338 - made ok to pour 3rd floor with sp insp approvals
INSP - Framing/Rough-in2/26/19992/26/19992/26/1999 PART
Details
02/25/99 338 - WALKED THE 2ND FLOOR DECK OBSERVED THE INSTALL OF THE FLO
INSP-Conference2/1/19992/1/19992/1/1999PPART
DetailsRick Jackson
no sprinkler plans
INSP - Framing/Rough-in1/26/19991/27/19991/27/1999APART
Details
JAY ###-#### REBAR bond beam made ok with sp insp approval
INSP - Framing/Rough-in1/15/19991/19/19991/19/1999APART
Details
01/19/99 338 - made ok with sp insp approval
INSP - Framing/Rough-in1/13/19991/14/19991/14/1999APART
Details
01/14/99 338 - MADE OK WITH SP INSP APPROVAL
INSP - Framing/Rough-in1/12/19991/12/19991/12/1999PPART
Details
01/12/99 333 - masonry ol
INSP - Framing/Rough-in1/8/19991/11/19991/11/1999APART
Details
01/11/99 338 - made k with sp insp approval
INSP - Framing/Rough-in1/5/19991/6/19991/6/1999APART
Details
01/06/99 333 - JAY ###-#### REBAR
INSP - Framing/Rough-in12/28/199812/29/199812/29/1998APART
Details
12/29/98 333 - masonry pour ok
INSP - Framing/Rough-in12/17/199812/18/199812/18/1998APART
Details
12/18/98 333 - OK PEND SPECIAL INSP REPORT
INSP - Framing/Rough-in12/11/199812/14/199812/14/1998APART
Details
12/14/98 333 - 12 foot ok
INSP - Framing/Rough-in12/8/199812/9/199812/9/1998APART
Details
12/09/98 333 - masonry ok
INSP - Framing/Rough-in12/7/199812/8/199812/8/1998APART
Details
12/08/98 333 - second pour ok pend special insp reports
INSP - Framing/Rough-in12/1/199812/2/199812/2/1998APART
Details
12/02/98 333 - first pour of masonry pending special insp reports
INSP - Framing/Rough-in11/30/199812/1/199812/1/1998APART
Details
12/01/98 333 - stem wall
INSP - Framing/Rough-in11/24/199811/25/199811/25/1998APART
Details
11/25/98 333 - stem wall insp
INSP - Foundation11/19/199811/20/199811/20/1998APART
Details
11/20/98 333 - stem wall ok pend special insp report