INSP - Final | 1/7/1999 | 1/8/1999 | 1/8/1999 | A | CANC |
Joe Tawney
|
|
|
01/08/99 406 - steve ###-#### CANCEL SHOULD BE 338 STRUCTURAL INSP
|
Permanent Occupancy | | 1/8/1999 | 1/8/1999 | | DONE |
|
|
|
|
INSP-Final Inspection | 1/6/1999 | 1/7/1999 | 1/7/1999 | A | PASS |
Joe Tawney
|
|
|
01/07/99 406 - steve- ###-#### call 1st before insp? fn fire-re-insp REINSP OK FOR CERT OF COMPLETION
|
INSP-Final Inspection | 12/22/1998 | 12/22/1998 | 12/23/1998 | P | FAIL |
Joe Tawney
|
|
|
12/23/98 406 - steve ###-#### fn fire FINAL FAIL FIRE EXT, RATED DRS, EMERG LIGHTS., EXIT SIGNS, SPKLRS
|
INSP - Final | 12/22/1998 | 12/22/1998 | 12/22/1998 | P | FAIL |
|
|
|
12/22/98 338 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Framing/Rough-in | 12/14/1998 | 12/14/1998 | 12/15/1998 | P | PART |
|
|
|
12/15/98 338 - made ok to tape the corridor tunnel ceiling
|
INSP - Framing/Rough-in | 11/25/1998 | 11/25/1998 | 11/27/1998 | P | PART |
|
|
|
11/25/98 338 - STEVE -###-#### GRID CEILING INSP need diffuser coinnecti
|
INSP - Framing/Rough-in | 11/9/1998 | 11/9/1998 | 11/9/1998 | P | PART |
|
|
|
11/09/98 338 - made ok to cover the new walls discussion on the tunnel c
|
INSP - Framing/Rough-in | 11/5/1998 | 11/6/1998 | 11/6/1998 | P | NR |
Carl Dependahl
|
|
|
Scheduled by Hello!....unable to contact/locate. 338 area
|