INSP - Final | 4/22/1999 | 4/23/1999 | 4/23/1999 | A | PASS |
Carl Dependahl
|
|
|
04/23/99 340 - Bill ###-####
|
INSP - Final | 12/30/1998 | 12/31/1998 | 12/31/1998 | A | FAIL |
Wes Worcester
|
|
|
12/31/98 342 - BILL ###-#### need mech and finish roof over garage
|
INSP - Framing/Rough-in | 12/15/1998 | 12/16/1998 | 12/16/1998 | A | PART |
Carl Dependahl
|
|
|
BILL ###-#### RE-INSP-SHEET ROCK TAPING; common wall fastened ok; need patch/repair wall adjacent to south side.
|
INSP - Framing/Rough-in | 12/14/1998 | 12/14/1998 | 12/14/1998 | A | PART |
Carl Dependahl
|
|
|
need complete insul package at hse/ gar
|
INSP - Framing/Rough-in | 12/11/1998 | 12/11/1998 | 12/11/1998 | P | PART |
Carl Dependahl
|
|
|
BILL ###-#### REINSPECT ...need to complete insul/ sealing. ok to cover at 1hr walls/ as noted.
|
INSP - Framing/Rough-in | 12/10/1998 | 12/10/1998 | 12/10/1998 | | PART |
Wes Worcester
|
|
|
12/10/98 342 - given to Carl
|
INSP - Framing/Rough-in | 12/9/1998 | 12/10/1998 | 12/10/1998 | A | FAIL |
Carl Dependahl
|
|
|
BILL- ###-#### CALL 1ST BEFORE INSP FR c/n, fire blocks,seal 1hr const, add gyp at ext 1hr walls...will consult Bob if ok to delete until adjacent unit goes in. ok to insul.
|
INSP - Framing/Rough-in | 12/8/1998 | 12/8/1998 | 12/8/1998 | P | FAIL |
Carl Dependahl
|
|
|
conf only re frame insp, need complete other insp's
|
INSP - Foundation | 11/18/1998 | 11/18/1998 | 11/18/1998 | P | PART |
Carl Dependahl
|
|
|
poured, appears ok.
|
INSP - Framing/Rough-in | 11/18/1998 | 11/18/1998 | 11/18/1998 | P | NR |
Carl Dependahl
|
|
|
BILL ###-#### FR INSP...nr need all other insp's; met w/owner, discussed 1hr wall req's at prop line. mis-called as frame
|