INSP - Final | 5/27/1999 | 5/27/1999 | 5/26/1999 | P | PASS |
Jim Storey
|
|
|
05/27/99 301 - Steve ###-####
|
INSP - Final | 5/25/1999 | 5/26/1999 | 5/26/1999 | A | FAIL |
Jim Storey
|
|
|
05/26/99 301 - Homeco ###-####
|
INSP - Framing/Rough-in | 2/17/1999 | 2/18/1999 | 2/19/1999 | A | PASS |
Jim Storey
|
|
|
02/18/99 301 - FRAM-OK FRAMING insulation ok sheer nailling ok
|
INSP - Framing/Rough-in | 2/12/1999 | 2/16/1999 | 2/16/1999 | A | FAIL |
Jim Storey
|
|
|
02/16/99 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 2/9/1999 | 2/10/1999 | 2/10/1999 | P | FAIL |
Jim Storey
|
|
|
02/10/99 301 - Scheduled by Hello!. Contact phone is [8507740].
|
INSP - Foundation | 12/30/1998 | 12/31/1998 | 12/31/1998 | A | PASS |
Jim Storey
|
|
|
12/31/98 301 - FDN -OK FOUNDATION
|
INSP - Foundation | 12/18/1998 | 12/18/1998 | 12/18/1998 | P | FAIL |
Russ Owen
|
|
|
12/18/98 407 - MTI Compation report on site only 93 % in some areas.
|
INSP - Foundation | 12/16/1998 | 12/17/1998 | 12/17/1998 | A | FAIL |
Russ Owen
|
|
|
12/17/98 407 - need approved plans for set backs to be determined.
|
INSP - Foundation | 12/1/1998 | 12/1/1998 | 12/1/1998 | P | PART |
Jim Storey
|
|
|
12/01/98 301 - footing ok rebar ok compaction report recieved and approv
|
INSP - Framing/Rough-in | 2/16/1999 | 2/17/1999 | 2/17/1998 | P | CANC |
Jim Storey
|
|
|
02/17/99 301 - ###-#### dennis framing
|