BLD-Final | 1/10/2000 | 1/10/2000 | 1/10/2000 | P | PART |
Russ Owen
|
|
|
Pending engineers approval of special inspection report.
|
FIRE-Final Inspection | 12/9/1999 | 12/10/1999 | 12/10/1999 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/09/1999 at 09:44:34. Contact: ###-####. Occupancy approved.
|
FIRE-Sprinkler Rough-in | 12/2/1999 | 12/2/1999 | 12/2/1999 | P | FAIL |
Rick Jackson
|
|
|
hydro stat test alan ###-#### unit 200 Hydro okay; sway bracing; FDC.
|
FIRE-Conference | 11/3/1999 | 11/3/1999 | 11/3/1999 | A | PART |
Rick Jackson
|
|
|
Addressing problem; sprinkler issues.
|
BLD-Framing/Rough-in | 9/22/1999 | 9/23/1999 | 9/23/1999 | A | PART |
Russ Owen
|
|
|
mike ###-#### Upper parapet frame
|
INSP - Framing/Rough-in | 7/16/1999 | 7/16/1999 | 7/16/1999 | P | PART |
Russ Owen
|
|
|
rebar masonary r/i mike ###-#### subject to special inspection.
|
INSP - Concrete | 5/19/1999 | 5/20/1999 | 5/20/1999 | P | PART |
Russ Owen
|
|
|
05/20/99 407 - subject to special inspection.
|
INSP - Concrete | 5/19/1999 | 5/20/1999 | 5/20/1999 | A | PART |
Russ Owen
|
|
|
05/20/99 407 - subject to special inspection.
|
INSP - Concrete | 5/20/1999 | 5/20/1999 | 5/20/1999 | | PART |
Russ Owen
|
|
|
05/20/99 407 - special inspection reqd. ok pending.
|
INSP - Foundation | 4/29/1999 | 4/30/1999 | 4/30/1999 | P | PART |
Russ Owen
|
|
|
04/30/99 407 - ok,called mike special inspector,will be on site.
|