BLD-Final | 10/28/1999 | 10/28/1999 | 10/28/1999 | P | PASS |
Wes Worcester
|
|
|
JOHN ###-#### DOOR GOING OUT BACK GARAGE KEY ON LIGHT FIXTURE NEXT TO THAT DOOR C/C issued
|
BLD-Final | 10/22/1999 | 10/22/1999 | 10/22/1999 | P | FAIL |
Wes Worcester
|
|
|
JOHN ###-#### FN OCC---GO TO BACK DOOR OF GARAGE- KEY-ON LIGHT FIXTURE NEXT TO DOOR--- BCEC, handrail incorrectly attached
|
BLD-Grading Inspection | 10/22/1999 | 10/22/1999 | 10/22/1999 | | PASS |
Rita DeYoung
|
|
|
Recieved engineer's letter certifying final grading. Final grading is as approved. Storm drain connection is correct.
|
INSP - Energy code compliance | 5/13/1999 | 5/14/1999 | 5/14/1999 | A | PASS |
Wes Worcester
|
|
|
05/14/99 342 - john ###-####
|
INSP - Framing/Rough-in | 5/3/1999 | 5/3/1999 | 5/3/1999 | P | PASS |
Wes Worcester
|
|
|
05/03/99 342 - John ###-####
|
INSP - Framing/Rough-in | 4/27/1999 | 4/27/1999 | 4/27/1999 | P | FAIL |
Wes Worcester
|
|
|
04/27/99 342 - ###-#### JOHN//FRAMING CALL B4 GOING TO MEET U no answer,
|
INSP - Foundation | 2/16/1999 | 2/16/1999 | 2/17/1999 | P | PART |
|
|
|
02/16/99 338 - madeok to pour the found r-bar is placed
|
INSP - Foundation | 2/12/1999 | 2/12/1999 | 2/12/1999 | | PART |
Carl Dependahl
|
|
|
02/12/99 340 - ###-#### JACK...ftgs, rec'd eng's site ok
|