INSP - Final | 4/15/1999 | 4/15/1999 | 4/15/1999 | P | PASS |
Russ Owen
|
|
|
04/15/99 407 - Scheduled by Hello!. Contact phone is [2303001].
|
INSP - Final | 4/8/1999 | 4/8/1999 | 4/8/1999 | P | FAIL |
Russ Owen
|
|
|
left corrections.o!. Contact phone is [2303001].
|
INSP - Energy code compliance | 3/2/1999 | 3/3/1999 | 3/3/1999 | P | PASS |
Russ Owen
|
|
|
Scheduled by Hello!. Contact phone is [2303001].
|
INSP - Energy code compliance | 3/3/1999 | 3/3/1999 | 3/3/1999 | | PASS |
Russ Owen
|
|
|
03/03/99 407 - Scheduled by Hello!. Contact phone is [2303001].
|
INSP - Framing/Rough-in | 3/1/1999 | 3/2/1999 | 3/2/1999 | A | FAIL |
Russ Owen
|
|
|
03/02/99 407 - steve ###-#### fr insp
|
INSP - Framing/Rough-in | 2/25/1999 | 2/26/1999 | 2/25/1999 | P | |
Russ Owen
|
|
|
Scheduled by Hello!. Contact phone is [2303001].
|
INSP - Framing/Rough-in | 2/18/1999 | 2/19/1999 | 2/19/1999 | A | PASS |
Russ Owen
|
|
|
02/19/99 407 - ok to side.
|
INSP - Foundation | 2/4/1999 | 2/4/1999 | 2/4/1999 | P | FAIL |
Russ Owen
|
|
|
02/04/99 407 - walls poured prior to 4:00pm inspection .
|
INSP - Concrete | 2/2/1999 | 2/3/1999 | 2/3/1999 | P | NR |
Russ Owen
|
|
|
TIME NOW 1:45PM, not a single foarm board in place.
|
INSP - Foundation | 2/3/1999 | 2/3/1999 | 2/3/1999 | P | NR |
Russ Owen
|
|
|
Now back again at 3:30pm ,Exterior foarms are not complete,steel not inplace,no interior foarms in place. job is not ready for inspection.(this is the second time I have been to this site this afternoon).
|
INSP - Concrete | 2/2/1999 | 2/2/1999 | 2/2/1999 | P | CANC |
Russ Owen
|
|
|
02/03/99 407 - cancell by contractor.
|