INSP - Final | 6/28/1999 | 6/29/1999 | 6/28/1999 | A | PASS |
|
|
|
06/29/99 338 - madeok l/c issued need plmg final on plmg div req xtra pe
|
INSP - Framing/Rough-in | 6/21/1999 | 6/22/1999 | 6/22/1999 | A | FAIL |
|
|
|
06/22/99 338 - CONF ON THE EXT LANDING AND STAIRS AT THE 2ND FLOOR LIVIN
|
INSP - Framing/Rough-in | 6/14/1999 | 6/15/1999 | 6/15/1999 | A | FAIL |
|
|
|
06/15/99 338 - other agencies not approved
|
INSP - Framing/Rough-in | 5/19/1999 | 5/20/1999 | 5/24/1999 | P | PART |
|
|
|
05/20/99 338 - made ok to cover framing
|
INSP - Energy code compliance | 5/19/1999 | 5/19/1999 | 5/19/1999 | P | PASS |
|
|
|
05/19/99 338 - madeok for the insulation
|
INSP - Framing/Rough-in | 5/19/1999 | 5/19/1999 | 5/19/1999 | P | PART |
|
|
|
05/19/99 338 - need more info on the fix in the garage and the truss han
|
INSP - Framing/Rough-in | 5/17/1999 | 5/18/1999 | 5/18/1999 | A | PART |
|
|
|
###-#### DON//FIRE WALL RIDGE ON ROOF made ok to install the rest of the roof decking
|
INSP - Framing/Rough-in | 5/13/1999 | 5/14/1999 | 5/14/1999 | A | FAIL |
Wes Worcester
|
|
|
05/14/99 342 - robert ###-#### mech, trusses, shr, lvl specs etc
|
INSP - Framing/Rough-in | 5/12/1999 | 5/13/1999 | 5/13/1999 | A | FAIL |
Wes Worcester
|
|
|
05/13/99 342 - Robert ###-#### need mech, plan notes, engineering, etc
|
INSP - Foundation | 3/30/1999 | 3/30/1999 | 3/30/1999 | P | PASS |
Wes Worcester
|
|
|
03/30/99 342 - ###-#### DUANE//WALL 1:00 PLEASE check for plans reading plans to remain on jobsite at all times. 338
|
INSP - Foundation | 3/30/1999 | 3/30/1999 | 3/30/1999 | | PART |
|
|
|
/ / 338 - NEED PLANS MARKED THESE PLANS TO BE ON JOBSITE AT ALL TIMES
|
INSP - Foundation | 3/29/1999 | 3/29/1999 | 3/29/1999 | P | PART |
|
|
|
03/29/99 338 - need approved plans on the jobsite
|