BLD-Final | 10/22/1999 | 10/22/1999 | 10/22/1999 | A | PASS |
|
|
|
Signed perm. col. occ. req. card.
|
FIRE-Final Inspection | 10/21/1999 | 10/21/1999 | 10/21/1999 | A | PASS |
Rick Jackson
|
|
|
occupancy approved
|
BLD-Final | 10/15/1999 | 10/15/1999 | 10/15/1999 | P | PASS |
|
|
|
wALTER ###-#### Ok by 409
|
INSP - Final | 8/23/1999 | 8/24/1999 | 8/24/1999 | A | PART |
|
|
|
08/24/99 338 - made ok for temp occ c/n issued
|
INSP - Final | 8/20/1999 | 8/23/1999 | 8/23/1999 | P | FAIL |
|
|
|
WALTER ###-####. TEMP. OCCUPANCY OTHER AGENCIES NOT APPROVED
|
INSP-Final Inspection | 8/23/1999 | 8/23/1999 | 8/23/1999 | P | PART |
Rick Jackson
|
|
|
1:30 for final alarms and sprinklers tested okay; need to complete main entrance, maintain exits until exterior complete
|
INSP-Final Inspection | 8/18/1999 | 8/20/1999 | 8/20/1999 | P | NR |
Rick Jackson
|
|
|
AFTER 12:00 TEMP OCC WALTER ###-#### alarm panel not working for pre-action/alarms
|
INSP-Final Inspection | 7/21/1999 | 7/22/1999 | 7/22/1999 | A | PART |
Rick Jackson
|
|
|
fire sprinkler overhead hydro - not a final; need copper system completed not
|
INSP - Framing/Rough-in | 7/16/1999 | 7/19/1999 | 7/19/1999 | A | PART |
|
|
|
07/19/99 338 - conf with kevin doing the ceiling grid system spoke about
|
INSP - Framing/Rough-in | 6/1/1999 | 6/1/1999 | 6/1/1999 | P | PASS |
|
|
|
06/01/99 338 - made ok to cover with other agencies blessing
|
INSP-Supply line flush | 5/26/1999 | 5/26/1999 | 5/26/1999 | A | PASS |
Rick Jackson
|
|
|
okay
|