INSP - Final | 7/20/1999 | 7/20/1999 | 7/20/1999 | | PASS |
|
|
|
/ / 338 - L/C ISSUED # 16419
|
INSP - Final | 7/19/1999 | 7/19/1999 | 7/19/1999 | P | FAIL |
|
|
|
07/19/99 338 - c/n issued other agencies not approved plm c/n on front w
|
INSP - Framing/Rough-in | 6/17/1999 | 6/18/1999 | 6/18/1999 | A | FAIL |
|
|
|
06/18/99 338 - wrong permit called in
|
INSP - Framing/Rough-in | 6/15/1999 | 6/16/1999 | 6/18/1999 | A | FAIL |
|
|
|
06/16/99 338 - fail as wron permit called in
|
INSP - Energy code compliance | 6/14/1999 | 6/14/1999 | 6/14/1999 | P | FAIL |
|
|
|
06/14/99 338 - madeok to start drywall c/n issued mech c/n in force
|
INSP - Framing/Rough-in | 6/10/1999 | 6/11/1999 | 6/11/1999 | P | PART |
Wes Worcester
|
|
|
06/11/99 342 - late pm Robert ###-#### fire caulk all membrane penetrati
|
INSP - Wall cover | 5/13/1999 | 5/13/1999 | 5/13/1999 | P | FAIL |
Wes Worcester
|
|
|
1-hour prop line wall problems walls must be complete to the roof deck with proper nailing per approved plans stair landing to be installed after that portion of the rated wall is completed on site were mjo, mp,301,305,325, and 342. All corrections were posted on the north unit.
|
INSP - Framing/Rough-in | 5/11/1999 | 5/12/1999 | 5/12/1999 | P | PART |
Wes Worcester
|
|
|
05/12/99 342 - fire wall late pm robert ###-#### blking for nailing in u
|
INSP - Framing/Rough-in | 5/7/1999 | 5/7/1999 | 5/7/1999 | P | PART |
Wes Worcester
|
|
|
fire wall/###-#### ok,stairs and demising walls wrong,trusses perpendicular
|
INSP - Framing/Rough-in | 5/5/1999 | 5/6/1999 | 5/6/1999 | P | FAIL |
Wes Worcester
|
|
|
05/06/99 342 - fire wall/ Don ###-#### being built as a duplex w/o conve
|
INSP - Framing/Rough-in | 4/30/1999 | 4/30/1999 | 4/30/1999 | P | PART |
Wes Worcester
|
|
|
04/30/99 342 - ###-#### DON//FIREWALL ok
|
INSP - Framing/Rough-in | 4/27/1999 | 4/28/1999 | 4/28/1999 | A | PASS |
Wes Worcester
|
|
|
04/28/99 342 - ###-#### DON//FIRE WALL
|
INSP - Foundation | 3/31/1999 | 3/31/1999 | 3/31/1999 | P | |
|
|
|
footing ###-####
|