BLD-Final | 4/10/2000 | 4/11/2000 | 4/11/2000 | A | FAIL |
Jim Storey
|
|
|
###-#### hand rails not code comlient. 4/11/00
|
BLD-Final | 4/11/2000 | 4/11/2000 | 4/11/2000 | P | PASS |
Russ Owen
|
|
|
###-#### Rear deck included, note inside handrails appears temporary. 4/12/00 10:23:17 AM
|
BLD-Final | 4/10/2000 | 4/10/2000 | 4/10/2000 | P | FAIL |
Russ Owen
|
|
|
val ###-####
|
BLD-Final | 4/6/2000 | 4/7/2000 | 4/7/2000 | A | FAIL |
Russ Owen
|
|
|
Val ###-####
|
BLD-Grading Inspection | 4/7/2000 | 4/7/2000 | 4/7/2000 | | PASS |
Rita DeYoung
|
|
|
Final grading is complete and according to plan. Acceptable compaction test results were provided for the house footings. However, compaction testing was not done in the area where a deck pier was placed and the deck is experiencing settlement problems. The contractor has indicated that the deck will be removed and replaced after the subgrade has been compacted and tested.
|
BLD-Final | 3/28/2000 | 3/29/2000 | 3/29/2000 | P | FAIL |
Wes Worcester
|
|
|
###-#### Need public works still. 3/30/00 10:55:11 AM
|
BLD-Final | 3/24/2000 | 3/27/2000 | 3/27/2000 | P | FAIL |
Wes Worcester
|
|
|
Val ###-#### Hillside conditions, hand rails, numbers, guard rail & self closing door. 3/28/00 9:05:43 AM
|
BLD-Energy code compliance | 1/14/2000 | 1/18/2000 | 1/18/2000 | A | PASS |
Wes Worcester
|
|
|
|
BLD-Framing/Rough-in | 1/14/2000 | 1/18/2000 | 1/18/2000 | A | PASS |
Wes Worcester
|
|
|
VAL ###-####
|
BLD-Energy code compliance | 1/13/2000 | 1/14/2000 | 1/14/2000 | P | NR |
Russ Owen
|
|
|
late pm Vapor barrier at upper floor not done. 1/18/00 8:51:30 AM
|
BLD-Framing/Rough-in | 1/13/2000 | 1/14/2000 | 1/14/2000 | P | FAIL |
Russ Owen
|
|
|
val ###-#### Complete corrections and recall. 1/18/00 8:52:25 AM
|
BLD-Framing/Rough-in | 1/11/2000 | 1/12/2000 | 1/12/2000 | A | FAIL |
Russ Owen
|
|
|
val-- ###-#### fr insp. C/N posted.
|
BLD-Framing/Rough-in | 1/4/2000 | 1/5/2000 | 1/5/2000 | A | NR |
Russ Owen
|
|
|
val ###-####. Need to have electrical approved.
|
BLD-Framing/Rough-in | 12/15/1999 | 12/15/1999 | 12/15/1999 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/15/1999 at 09:56:15. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/22/1999 | 10/22/1999 | 10/22/1999 | P | PASS |
Jim Storey
|
|
|
SHEAR WALL VAL ###-#### Shear exterior ok
|
BLD-Framing/Rough-in | 10/18/1999 | 10/19/1999 | 10/19/1999 | A | FAIL |
Wes Worcester
|
|
|
VAL--- ###-#### FR INSP 407's area; C/N nailing etc.
|
INSP - Foundation | 8/10/1999 | 8/10/1999 | 8/10/1999 | P | PASS |
Russ Owen
|
|
|
08/10/99 407 - footing val ###-####
|
INSP - Foundation | 8/5/1999 | 8/5/1999 | 8/5/1999 | P | FAIL |
Russ Owen
|
|
|
08/05/99 407 - left correction.
|
INSP - Foundation | 7/20/1999 | 7/21/1999 | 7/21/1999 | A | PASS |
Russ Owen
|
|
|
07/21/99 407 - VAL ###-#### GARAGE FOOTING. 1ST THING IN AM.PER YOU.
|
INSP - Foundation | 6/1/1999 | 6/2/1999 | 6/2/1999 | A | PASS |
Russ Owen
|
|
|
06/02/99 407 - as per engineers site visit walls.
|
INSP - Foundation | 6/1/1999 | 6/1/1999 | 6/1/1999 | P | PART |
Russ Owen
|
|
|
06/01/99 407 - TALKED WITH THE ENGINEER,WHO WENT OUT TO EXAMINE WALLS,i
|
INSP - Foundation | 6/1/1999 | 6/1/1999 | 6/1/1999 | A | FAIL |
Russ Owen
|
|
|
NEED ENGINEER TO FIELD INSPECT,WALLS OF,ALSO PENDING COMPACTION REPORT.
|
INSP - Foundation | 5/27/1999 | 5/27/1999 | 5/27/1999 | P | NR |
Russ Owen
|
|
|
05/27/99 407 - not ready.
|
INSP - Foundation | 5/19/1999 | 5/19/1999 | 5/19/1999 | P | PASS |
Russ Owen
|
|
|
05/19/99 407 - Footings - Rick Brokaw, ###-####
|