BLD-Final | 11/29/1999 | 11/30/1999 | 11/30/1999 | P | PASS |
|
|
|
rich ###-#### Other agencies approved signed perm. Col.
|
FIRE-Final Inspection | 11/29/1999 | 11/30/1999 | 11/30/1999 | A | PASS |
Rick Jackson
|
|
|
rich ###-####
|
Permanent Occupancy | | 11/30/1999 | 11/30/1999 | | DONE |
|
|
|
|
INSP - Final | 8/12/1999 | 8/13/1999 | 8/13/1999 | A | PART |
|
|
|
08/13/99 338 - rich-- ###-#### fn occ insp
|
INSP - Final | 8/11/1999 | 8/12/1999 | 8/12/1999 | P | FAIL |
|
|
|
08/12/99 338 - other agencies not approved
|
INSP-Final Inspection | 8/12/1999 | 8/12/1999 | 8/12/1999 | P | PART |
Rick Jackson
|
|
|
suite number
|
INSP-Final Inspection | 8/11/1999 | 8/12/1999 | 8/12/1999 | A | NR |
Rick Jackson
|
|
|
###-#### not ready
|
INSP-Conference | 8/6/1999 | 8/6/1999 | 8/6/1999 | A | PART |
Rick Jackson
|
|
|
discussed with general contractor about medgas certification; received call from sub contractor about requirements - relayed NFPA 99 requirements
|
INSP - Framing/Rough-in | 7/19/1999 | 7/20/1999 | 7/20/1999 | P | PART |
|
|
|
07/20/99 338 - made ok to drop in tiles spreADERS ARE IN
|
INSP - Framing/Rough-in | 7/16/1999 | 7/16/1999 | 7/16/1999 | | PART |
|
|
|
07/16/99 338 - made ok to install borders c/n issued
|
INSP - Framing/Rough-in | 6/7/1999 | 6/7/1999 | 6/7/1999 | P | PART |
|
|
|
###-#### RICH//FRAMING MADE OK TO COVER SOUTH 1/2 OF THE 2ND FLOOR UP TO THE CORRIDOR WITH ELE INSP APPROVALS
|