BLD-Final | 6/22/2000 | 6/22/2000 | 6/22/2000 | P | PASS |
Carl Dependahl
|
|
|
1hr construction of exterior wall will be completed as tenent improvements are made.
|
BLD-Final | 6/7/2000 | 6/7/2000 | 6/7/2000 | P | FAIL |
Carl Dependahl
|
|
|
steve ###-#### c/n fail; 1 hr wall & LID, other sig's 6/19/00 11:35:43 AM
|
BLD-Framing/Rough-in | 12/3/1999 | 12/6/1999 | 12/6/1999 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/03/1999 at 10:55:30. Contact: ###-####. Shell framing: need 5/8 gyp @ eave @ west in lieuof- blocks- ok to cover mech. Rm.
|
BLD-Footing | 11/5/1999 | 11/8/1999 | 11/8/1999 | A | PART |
Carl Dependahl
|
|
|
CHUCK --###-#### FT INSP Setback (FTG) ok per verbal W/Mike Otto. Pour @ own risk.
|
BLD-Foundation | 11/2/1999 | 11/3/1999 | 11/3/1999 | P | FAIL |
|
|
|
###-#### kevin Poured w/o insp.
|
BLD-Footing | 11/1/1999 | 11/2/1999 | 11/2/1999 | A | PART |
Carl Dependahl
|
|
|
kevin-- ###-#### ft insp
|
BLD-Foundation | 10/29/1999 | 11/1/1999 | 11/1/1999 | A | PART |
Carl Dependahl
|
|
|
foundation wall kevin ###-#### North 1/2 bld A, fnd. Walls ok
|
BLD-Footing | 10/28/1999 | 10/29/1999 | 10/29/1999 | P | PART |
Carl Dependahl
|
|
|
kevin-- ###-#### ft insp North 1/2 bldg. A, ftg. Ok
|
INSP-Final Inspection | 8/12/1999 | 8/12/1999 | 8/12/1999 | P | PART |
Rick Jackson
|
|
|
suite number
|