BLD-Final | 6/22/2000 | 6/22/2000 | 6/22/2000 | P | PASS |
Carl Dependahl
|
|
|
1hr construction of wall will be completed with tenent improvements.
|
BLD-Final | 6/7/2000 | 6/7/2000 | 6/7/2000 | P | FAIL |
Carl Dependahl
|
|
|
steve ###-#### c/n fail; other sig's - 1 hr wall/ LID 6/19/00 11:36:24 AM
|
FIRE-Final Inspection | 6/1/2000 | 6/1/2000 | 6/1/2000 | P | PASS |
Joe Tawney
|
|
|
###-#### Final ok for cert. of completion. 6/5/00 10:18:04 AM
|
FIRE-Final Inspection | 5/30/2000 | 5/31/2000 | 5/31/2000 | A | PASS |
Joe Tawney
|
|
|
###-#### Reinsp. ok for certificate of completion. 5/31/00 4:32:09 PM
|
BLD-Final | 5/19/2000 | 5/22/2000 | 5/22/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/19/2000 at 13:48:33. Contact: ###-####.
|
FIRE-Final Inspection | 5/19/2000 | 5/22/2000 | 5/22/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 05/19/2000 at 13:46:51. Contact: ###-####. Final fail C/N issued. 5/23/00 2:19:02 PM
|
BLD-Framing/Rough-in | 1/13/2000 | 1/13/2000 | 1/13/2000 | A | FAIL |
Carl Dependahl
|
|
|
Keep C/N; recall.
|
BLD-Conference | 1/11/2000 | 1/11/2000 | 1/11/2000 | A | PASS |
Carl Dependahl
|
|
|
w/Bldr. (framer) re: C/N of 1/10/00.
|
BLD-Framing/Rough-in | 1/7/2000 | 1/10/2000 | 1/10/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/07/2000 at 12:54:37. Contact: ###-####. Bldg. B- C/N: trusses, 1hr const. Must be installed @ P.L.
|
BLD-Framing/Rough-in | 12/6/1999 | 12/6/1999 | 12/6/1999 | A | PART |
Carl Dependahl
|
|
|
Underfloor & joists ok.
|
BLD-Footing | 11/10/1999 | 11/10/1999 | 11/10/1999 | P | PART |
Carl Dependahl
|
|
|
kevin ###-#### Bldg. B NW corner ftgs.
|
BLD-Foundation | 11/9/1999 | 11/9/1999 | 11/9/1999 | P | PART |
Carl Dependahl
|
|
|
kevin###-#### Delivered revised site plan; ok to shift 4' to East per P&Z.
|
BLD-Footing | 11/4/1999 | 11/5/1999 | 11/5/1999 | A | FAIL |
Russ Owen
|
|
|
KEVIN ###-#### Setbacks not per approved plans, left corrections posted.
|
BLD-Footing | 11/3/1999 | 11/4/1999 | 11/4/1999 | P | FAIL |
Alan Hauser
|
|
|
kevin ###-#### Cancelled by contractor
|