BLD-Final | 1/31/2000 | 2/1/2000 | 2/1/2000 | A | PASS |
Jim Sly
|
|
|
val ###-#### key above front door c\c 16026 2/1/00 3:08:11 PM
|
BLD-Final | 1/20/2000 | 1/21/2000 | 1/21/2000 | A | FAIL |
Jim Sly
|
|
|
val-- ###-#### fn -reinsp Complete prev. cor. 1/21/00 11:54:20 AM
|
BLD-Final | 12/6/1999 | 12/6/1999 | 12/6/1999 | P | FAIL |
Tom Arcoraci
|
|
|
val ###-#### See C/notice.
|
FIRE-Final Inspection | 12/2/1999 | 12/3/1999 | 12/3/1999 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/02/1999 at 11:09:11. Contact: ###-####. C/N need mech final, temp glazing, firecaulk garage.
|
INSP - Framing/Rough-in | 8/18/1999 | 8/19/1999 | 8/19/1999 | A | PASS |
Russ Owen
|
|
|
08/19/99 407 - CODY ###-#### REINSPECTION
|
INSP - Framing/Rough-in | 8/13/1999 | 8/16/1999 | 8/16/1999 | A | FAIL |
Jim Sly
|
|
|
08/16/99 316 - Complete prev corr.
|
INSP - Framing/Rough-in | 8/11/1999 | 8/11/1999 | 8/11/1999 | P | FAIL |
Tom Arcoraci
|
|
|
08/11/99 408 - cn issued ok to insulate
|
INSP - Framing/Rough-in | 8/9/1999 | 8/9/1999 | 8/9/1999 | P | FAIL |
Jim Sly
|
|
|
08/09/99 316 - C/N....Too many frame corr to list
|
INSP - Framing/Rough-in | 8/4/1999 | 8/4/1999 | 8/4/1999 | P | FAIL |
Wes Worcester
|
|
|
08/04/99 342 - eng incorrect on plan, need mech, need eng fix for overhe
|
INSP - Framing/Rough-in | 7/30/1999 | 7/30/1999 | 7/30/1999 | P | PART |
Jim Sly
|
|
|
07/30/99 316 - OK to side but need straps and diaphram interior....
|
INSP - Framing/Rough-in | 7/26/1999 | 7/27/1999 | 7/27/1999 | A | FAIL |
Jim Sly
|
|
|
07/27/99 316 - Shear wall C/N....Nailing and straps
|
INSP - Foundation | 5/24/1999 | 5/24/1999 | 5/24/1999 | P | PASS |
Jim Sly
|
|
|
05/24/99 316 -
|
INSP - Foundation | 5/20/1999 | 5/21/1999 | 5/21/1999 | A | PART |
Jim Sly
|
|
|
05/21/99 316 - Soil, foot width, height, footing rebar OK...setbks appea
|