BLD-Final | 5/18/2000 | 5/19/2000 | 5/19/2000 | A | PASS |
Carl Dependahl
|
|
|
does not open until 10:30\\###-#### Ok to sign @ office. 5/22/00 10:52:11 AM
|
Permanent Occupancy | | 5/19/2000 | 5/19/2000 | | DONE |
|
|
|
|
Permanent Occupancy | | 5/19/2000 | 5/19/2000 | | DONE |
|
|
|
|
BLD-Final | 12/17/1999 | 12/17/1999 | 12/17/1999 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/17/1999 at 09:05:50. Contact: ###-####. Struct. Ok; need P&Z (landscape to be done by owner).
|
BLD-Final | 11/16/1999 | 11/17/1999 | 11/17/1999 | P | FAIL |
Carl Dependahl
|
|
|
TIM ###-#### C/N need card.
|
FIRE-Final Inspection | 11/15/1999 | 11/16/1999 | 11/16/1999 | A | CANC |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 11/15/1999 at 12:45:22. Contact: ###-####. Completed on 11/15/99.
|
FIRE-Final Inspection | 11/12/1999 | 11/12/1999 | 11/15/1999 | P | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 11/12/1999 at 09:13:33. Contact: ###-####. Occupancy approval.
|
BLD-Framing/Rough-in | 9/27/1999 | 9/28/1999 | 9/28/1999 | A | PASS |
Tom Arcoraci
|
|
|
insulation inspection also / tim ###-####
|
BLD-Framing/Rough-in | 9/23/1999 | 9/24/1999 | 9/24/1999 | A | PART |
Carl Dependahl
|
|
|
REINSPECT TIM ###-#### Part, ok to insulate
|
BLD-Framing/Rough-in | 9/17/1999 | 9/17/1999 | 9/17/1999 | P | FAIL |
Carl Dependahl
|
|
|
c/n: Fireblocks, hold-downs, nailing, straps, no underfloor access, parapet wall, etc.
|
INSP - Foundation | 8/19/1999 | 8/23/1999 | 8/24/1999 | A | PART |
Carl Dependahl
|
|
|
08/23/99 340 - ###-####; c/n ok, pipe sleeved. walls
|
INSP - Foundation | 8/13/1999 | 8/16/1999 | 8/16/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/16/99 340 - TIM SCHINK--###-#### FT INSP-PLANS ARE INSIDE CRAFT STORE
|