Permanent Occupancy | | 12/21/2000 | 12/21/2000 | | DONE |
|
|
|
|
BLD-Final | 11/30/2000 | 12/1/2000 | 12/1/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/30/2000 at 17:19:30. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/27/2000 | 11/28/2000 | 11/28/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/27/2000 at 15:03:35. Contact: ###-####.
|
FIRE-Final Inspection | 11/17/2000 | 11/17/2000 | 11/21/2000 | P | PASS |
Rick Jackson
|
|
|
fire fn --danny-- cell-- ###-####
|
FIRE-Final Inspection | 11/15/2000 | 11/15/2000 | 11/15/2000 | P | NR |
Rick Jackson
|
|
|
###-#### ///Dan called, having troubles with the alarms and will reschedule 11/16/2000 9:50:26 AM
|
FIRE-Final Inspection | 11/6/2000 | 11/6/2000 | 11/6/2000 | P | FAIL |
Rick Jackson
|
|
|
###-#### alarms not ready; need paving and turn around completed; address 11/6/2000 3:57:26 PM
|
FIRE-Final Inspection | 11/2/2000 | 11/2/2000 | 11/2/2000 | P | NR |
Rick Jackson
|
|
|
DANNY -###-#### FIRE FN
|
BLD-Energy code compliance | 7/21/2000 | 7/24/2000 | 7/24/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/21/2000 at 18:00:30. Contact: ###-####. ele heater box out. 7/24/2000 10:12:15 AM
|
BLD-Framing/Rough-in | 7/19/2000 | 7/20/2000 | 7/20/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/19/2000 at 10:58:57. Contact: ###-####. framing ok pending others. 7/20/2000 12:41:12 PM
|
FIRE-Supply Line Cover | 11/9/1999 | 11/10/1999 | 11/10/1999 | P | PASS |
Rick Jackson
|
|
|
shelly ok to cover (not CPVC pipe).
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
|
|
|
|
FIRE-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Rick Jackson
|
|
|
|
BLD-Footing | 10/6/1999 | 10/7/1999 | 10/7/1999 | A | PART |
Tom Arcoraci
|
|
|
Preston ###-#### spec unsp on site
|