BLD-Final | 7/14/2000 | 7/14/2000 | 7/14/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/14/2000 at 10:50:56. Contact: ###-####.
|
Permanent Occupancy | | 7/14/2000 | 7/14/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/11/2000 | 7/12/2000 | 7/13/2000 | A | PASS |
Rick Jackson
|
|
|
frank ###-####; final pass
|
BLD-Energy code compliance | 2/16/2000 | 2/17/2000 | 2/17/2000 | A | PASS |
Jim Storey
|
|
|
Preston Baker ###-#### said that they spoke to you and that you would go out 2-16-00 pm Framing C/N ok insulation ok for cover. 2/17/00 2:14:06 PM
|
BLD-Energy code compliance | 2/15/2000 | 2/16/2000 | 2/16/2000 | A | FAIL |
Jim Storey
|
|
|
###-#### preston C/N posted. 2/17/00 10:05:29 AM
|
BLD-Framing/Rough-in | 2/9/2000 | 2/10/2000 | 2/10/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/09/2000 at 16:58:30. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/1/2000 | 2/2/2000 | 2/2/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/01/2000 at 15:59:30. Contact: ###-####. see corr. 2/3/00 8:11:07 AM
|
BLD-Framing/Rough-in | 1/11/2000 | 1/12/2000 | 1/12/2000 | A | FAIL |
Jim Storey
|
|
|
shilo ###-#### r/I. Sprinkler R/I inspection.
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
|
|
|
|
FIRE-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Rick Jackson
|
|
|
|
FIRE-Supply Line Cover | 10/28/1999 | 10/28/1999 | 10/28/1999 | P | PASS |
Rick Jackson
|
|
|
ok to cover
|
BLD-Foundation | 10/14/1999 | 10/15/1999 | 10/15/1999 | A | PART |
|
|
|
###-#### poured 10/14/99 w/o city insp.
|