BLD-Final | 11/30/2000 | 12/1/2000 | 12/1/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/30/2000 at 17:14:57. Contact: ###-####.
|
Permanent Occupancy | | 12/1/2000 | 12/1/2000 | | DONE |
|
|
|
|
BLD-Final | 8/31/2000 | 9/1/2000 | 9/1/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/31/2000 at 18:20:07. Contact: ###-####. pending p/v perm sign off. 9/1/2000 11:31:36 AM
|
BLD-Final | 8/30/2000 | 8/31/2000 | 8/31/2000 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/30/2000 at 13:41:26. Contact: ###-####.fire stopping not complet/door hard ware. 8/31/2000 3:21:20 PM
|
FIRE-Final Inspection | 8/31/2000 | 8/31/2000 | 8/31/2000 | P | PASS |
Rick Jackson
|
|
|
reinspection frank ###-####
|
FIRE-Final Inspection | 8/28/2000 | 8/29/2000 | 8/29/2000 | A | FAIL |
Rick Jackson
|
|
|
FRANK-- ###-#### FIRE FN alarms not working in all areas 8/29/2000 12:13:05 PM
|
FIRE-Final Inspection | 8/29/2000 | 8/29/2000 | 8/29/2000 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 8/29/2000 alarms not working right 8/30/2000 8:14:20 AM
|
BLD-Energy code compliance | 5/18/2000 | 5/18/2000 | 5/18/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 05/18/2000 at 06:30:50. Contact: ###-####.made ok to cover all prev sugg done 5/18/00 3:23:02 PM made ok to cover 5/18/00 3:53:55 PM
|
BLD-Framing/Rough-in | 5/12/2000 | 5/16/2000 | 5/16/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/12/2000 at 07:39:02. Contact: ###-####.
|
BLD-Energy code compliance | 5/10/2000 | 5/10/2000 | 5/10/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 05/10/2000 at 07:11:21. Contact: ###-####. ok to cover the south 1/2 only 5/10/00 11:30:45 AM
|
BLD-Framing/Rough-in | 5/3/2000 | 5/3/2000 | 5/3/2000 | P | PART |
Jim Storey
|
|
|
walk through Mike ###-#### south end of bldg framing ok ok to insulate 5/3/00 3:13:01 PM
|
FIRE-Supply Line Cover | 11/9/1999 | 11/10/1999 | 11/10/1999 | P | PASS |
Rick Jackson
|
|
|
shelly ###-#### ok to cover (not CPVC pipe).
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
|
|
|
|
FIRE-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Rick Jackson
|
|
|
|
BLD-Foundation | 10/6/1999 | 10/7/1999 | 10/7/1999 | A | PART |
Tom Arcoraci
|
|
|
Preston Baker ###-#### spec insp on site
|
BLD-Footing | 9/29/1999 | 9/30/1999 | 9/30/1999 | A | NR |
Jim Storey
|
|
|
Preston Baker ###-#### SI
|