Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-01726
StatusFinaled
Name RAFANELLI AND NAHAS
Site Address 1682 S LOGGERS POND PL
Project NameRIVER QUARRY APT
Customer Number 
ePlanReviewNo
Description
BUILDING # 14, TYPE II, 12 UNITS * TO CONSTRUCT A NEW THREE STORY, WOOD FRAMED, TYPE V ONE-HOUR, 12 UNIT APARTMENT BUILDING. THE FIRST FLOOR CONTAINS 4-ONE BEDROOM, ONE BATHROOM @ 790 SQ.FT EACH WITN 2684 SQ.FT OF GARAGE AREA. THE SECOND FLOOR CONTAINS 1-ONE BEDROOM ONE BATHROOM UNIT @ 790 SQ.FT. 2-TWO BEDROOM TWO BATHROOM UNIT @ 1146 SQ.FT. EACH. 1- THREE BEDROOM TWO BATHROOM UNIT @ 1344 SQ.FT. THE THIRD FLOOR CONTAINS 1-ONE-BEDROOM ONE BATHROOM UNIT @ 790 SQ.FT. 2-TWO BEDROOM TWO BATHROOM UNIT @ 1146 SQ.FT. EACH AND 1-THREE BEDROOM TWO BATHROOM UNIT AT 1344 SQ.FT. THE FIRST FLOOR IS APPROXIMATELY 3160 SQ.FT. FOR LIVING AREA THE SECOND FLOOR IS APPROXIMATELY 4426 SQ.FT. OF LIVING AREA THE THIRD FLOOR IS APPROXIMATELY 4426 SQ.FT. FOR LIVING AREA. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI A117.1 AND THE 1997 EDITION OF THE UBC. NOTE: THIS BUILDING IS FIRE SPRINKLERED PER NFPA 13-R. MJP (P.C.# 438-99)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/1/20015/1/20015/1/2001PPASS
DetailsJim Storey
mike ###-#### fn occ
Permanent Occupancy 5/1/20015/1/2001 DONE
Details
BLD-Final3/15/20013/16/20013/16/2001PPASS
DetailsJim Storey
###-#### final occ on pending p&z tenp sign off. 3/19/2001 12:30:36 PM
FIRE-Final Inspection3/16/20013/16/20013/16/2001APASS
DetailsRick Jackson
Added by Inspector: 409 On 3/16/2001 8:06:13 AM
BLD-Final3/9/20013/12/20013/12/2001PNR
DetailsJim Storey
###-####
BLD-Energy code compliance11/13/200011/14/200011/14/2000APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 11/13/2000 at 07:16:02. Contact: ###-####. ins ok, need redo pt on gas 11/14/2000 11:59:01 AM
FIRE-Supply Line Flush11/7/200011/8/200011/8/2000PCANC
DetailsRick Jackson
shelly ###-#### will reschedule for 11/9 11/7/2000 12:05:09 PM
FIRE-Supply Line Hydro11/7/200011/8/200011/8/2000PCANC
DetailsRick Jackson
shelly ###-#### will reschedule for 11/9 11/7/2000 12:05:24 PM
BLD-Energy code compliance11/2/200011/3/200011/3/2000PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/02/2000 at 13:50:59. Contact: ###-####. third floor ok 11/3/2000 3:07:22 PM
BLD-Framing/Rough-in10/16/200010/16/200010/16/2000ANR
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/16/2000 at 07:27:54. Contact: ###-####. bolts at occ roof/ strap at grage col. supports and plumbing/ bolts at leadger. 10/16/2000 11:06:48 AM
BLD-Conference11/9/199911/9/199911/9/1999APASS
DetailsJim Storey
BLD-Conference11/9/199911/9/199911/9/1999APASS
Details
FIRE-Conference11/9/199911/9/199911/9/1999APASS
DetailsRick Jackson