Permit Information
Permit NumberBLD99-01754
StatusFinaled
Name MIKE KRUGLY
Site Address 510 N MILWAUKEE ST
Project NameGATEWAY COUNTRY
Customer Number 
ePlanReviewNo
Description
GATEWAY COUNTRY * TO CONSTRUCT A NEW 6000 SQ. FT., ONE STORY RETAIL SHELL BUILDING AND RELATED SITE IMPROVEMENTS. THIS BUILDING SHELL IS CONSTRUCTED OF A CONCRETE SLAB FLOOR, MASONRY EXTERIOR WALLS AND STEEL STRUCTURAL FRAME AND ROOF DECK. THIS PERMIT IS FOR THE CONSTRUCTION OF A SHELL BUILDING ONLY; NO OCCUPANCY IS ALLOWED UNDER THIS PERMIT. A SEPARATE TENANT IMPROVEMENT PERMIT IS REQUIRED TO FINISH THIS BUILDING FOR OCCUPANCY. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LSIT. DRH99-0059/PC#449-99/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/25/199910/25/199910/25/1999PPASS
DetailsCarl Dependahl
GEORGE ###-#### FN INSP OCC L/C; shell only
BLD-Final10/22/199910/22/199910/22/1999PFAIL
DetailsCarl Dependahl
GEORGE ###-#### No plan onsite, left msg.
BLD-Final10/19/199910/19/199910/19/1999PFAIL
DetailsCarl Dependahl
George - final on shell, Cathy has the card at her desk & George has a photo-copy of occ. req. card Keep C/N; need egn's letter for final met w/contractor
BLD-Final10/14/199910/14/199910/14/1999PFAIL
DetailsCarl Dependahl
GEORGE--- ###-#### FN -FOR SHELL Need occ. Req. card- need PZ signoff rear X.T sign
FIRE-Final Inspection10/14/199910/14/199910/14/1999PPASS
DetailsJoe Tawney
GEORGE--- ###-#### FIRE FN Ok for cert. Of completion on shell
INSP - Framing/Rough-in9/9/19999/9/19999/9/1999PPART
DetailsCarl Dependahl
begin roof frame ... spec. insp req'd
INSP - Framing/Rough-in9/3/19999/7/19999/7/1999APART
DetailsCarl Dependahl
george maxwell ###-#### fn grouting cmu wall; 9/7 Grout, MTI onsite, pending insp. report. jrb;
INSP - Framing/Rough-in9/2/19999/3/19999/3/1999APART
DetailsCarl Dependahl
09/03/99 340 - george- ###-#### -cmu wall grount at 20 ftpend insp repor
INSP - Framing/Rough-in8/30/19998/31/19998/31/1999PPART
DetailsCarl Dependahl
08/31/99 340 - CMU WALL POUR GEORGE ###-#### POUR 15 FEET; mti onsite, p
INSP - Concrete8/27/19998/30/19998/30/1999APART
DetailsCarl Dependahl
08/30/99 340 - CMU GROUTED WALLS / GEORGE ###-####; mti onsite, pend rep
INSP - Framing/Rough-in8/24/19998/27/19998/27/1999PPART
DetailsCarl Dependahl
08/27/99 340 - george-- ###-#### grout wall insp; WIP, LOOKS OK, MTI ONS
INSP - Framing/Rough-in8/24/19998/26/19998/26/1999PPART
DetailsCarl Dependahl
08/26/99 340 - george ###-#### grout cmu wall insp; mti onsite, looks ok
INSP - Framing/Rough-in8/24/19998/25/19998/25/1999PPART
DetailsCarl Dependahl
08/26/99 340 - george-- ###-####-grout walls cmu -insp; met w/ mti insp.
INSP - Framing/ Rough-in8/24/19998/24/19998/24/1999 PART
DetailsCarl Dependahl
/ / 340 - MASONRY; MTI ONSITE
INSP - Concrete8/18/19998/18/19998/18/1999PPART
DetailsCarl Dependahl
08/18/99 340 - Scheduled by Hello!....SLAB
INSP - Foundation8/9/19998/10/19998/10/1999PPART
DetailsCarl Dependahl
08/10/99 340 - LATE PM. SCOTT ###-####; part walls,bar ok.
INSP - Foundation8/6/19998/6/19998/6/1999PPART
DetailsCarl Dependahl
08/06/99 340 - GEORGE ###-#### PART FTGS
INSP - Foundation8/4/19998/5/19998/5/1999AFAIL
DetailsCarl Dependahl
08/05/99 340 - need complete rebar. Contact phone is [6728125].