BLD-Final | 11/26/2001 | 11/26/2001 | 11/26/2001 | P | PASS |
Tony Young
|
|
|
fn --mary ###-#### -re-insp
|
BLD-Final | 11/16/2001 | 11/19/2001 | 11/19/2001 | P | FAIL |
Steven Webb
|
|
|
###-#### c/n given to owner--plumbing and electrical finals needed--I reviewed a letter from Boise Cascade in regards to the beam inspector 407 wrote about in a prior c/n.. It appears the beam in question (which is covered) should be adaquate for load bearing. 11/19/2001 4:07:49 PM
|
BLD-Final | 3/26/2001 | 3/26/2001 | 3/26/2001 | P | FAIL |
Tony Young
|
|
|
fn --for homeowner-- paula ###-####
conference on final inspection, smoke det., guard rail, finish trades, etc. 3/26/2001 12:15:54 PM
|
BLD-Framing/Rough-in | 9/24/1999 | 9/24/1999 | 9/24/1999 | P | NR |
Russ Owen
|
|
|
|
BLD-Framing/Rough-in | 9/21/1999 | 9/22/1999 | 9/22/1999 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/21/1999 at 12:06:06. Contact: ###-####. Need to expose beam over kitchen, also need all other approvals
|
INSP - Framing/Rough-in | 9/15/1999 | 9/15/1999 | 9/15/1999 | P | PART |
Russ Owen
|
|
|
CONFERENCE ONLY-HAVE INSTALLED 2ND FLOOR SUB-FLOOR AND HAS COVERED WORK, WILL NEED TO EXPOSE AREA OVER KITCHEN
|
INSP - Foundation | 8/2/1999 | 8/2/1999 | 8/2/1999 | | PART |
Wes Worcester
|
|
|
/ / 342 - FTG OK 342
|
INSP - Foundation | 8/2/1999 | 8/2/1999 | 8/2/1999 | P | PART |
Russ Owen
|
|
|
08/02/99 407 - pored before insp appars ok ,small addition.
|