BLD-Final | 2/2/2000 | 2/2/2000 | 2/2/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/02/2000 at 08:33:04. Contact: ###-####. c\c 17254 2/3/00 9:19:04 AM
|
BLD-Final | 1/28/2000 | 1/28/2000 | 1/28/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 01/28/2000 at 08:37:52. Contact: ###-####. left c\n 1/31/00 9:14:34 AM
|
BLD-Energy code compliance | 11/12/1999 | 11/15/1999 | 11/15/1999 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/12/1999 at 16:43:58. Contact: ###-####.
|
BLD-Energy code compliance | 11/11/1999 | 11/12/1999 | 11/12/1999 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/11/1999 at 16:52:55. Contact: ###-####. Not ready- left note.
|
BLD-Framing/Rough-in | 11/9/1999 | 11/10/1999 | 11/11/1999 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/09/1999 at 14:51:03. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/8/1999 | 11/9/1999 | 11/9/1999 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/08/1999 at 16:43:58. Contact: ###-####. C/N.. Need mech R/I air infiltr. And plans.
|
BLD-Framing/Rough-in | 10/21/1999 | 10/22/1999 | 10/22/1999 | A | PART |
Jim Sly
|
|
|
SHEAR WALL GREG ###-#### Shear wall nailing ok
|
BLD-Framing/Rough-in | 9/16/1999 | 9/17/1999 | 9/17/1999 | P | PART |
Jim Sly
|
|
|
H.D. straps nailed.. OK to add shear panels
|
INSP - Foundation | 7/30/1999 | 8/2/1999 | 8/2/1999 | P | PART |
Jim Sly
|
|
|
08/02/99 316 - Wall and rebar appears OK
|
INSP - Foundation | 7/30/1999 | 7/30/1999 | 7/30/1999 | P | PART |
Jim Sly
|
|
|
07/30/99 316 - Foot appears OK
|