BLD-Final | 1/11/2000 | 1/13/2000 | 1/13/2000 | P | PASS |
Alan Hauser
|
|
|
sheila ###-#### fn occ----code for gar 4213 for access CALL TO MEET THERE C/C #18238. 1/14/00 2:25:35 PM
|
BLD-Final | 1/10/2000 | 1/11/2000 | 1/11/2000 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 11:47:16. Contact: ###-####. Not ready.
|
BLD-Energy code compliance | 10/26/1999 | 10/26/1999 | 10/26/1999 | P | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 10/25/1999 | 10/26/1999 | 10/26/1999 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/25/1999 at 16:13:02. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/20/1999 | 10/21/1999 | 10/21/1999 | A | FAIL |
Jim Sly
|
|
|
shella ###-#### C/N.. Need blumb R/I approval and misc. frame corr.
|
BLD-Framing/Rough-in | 10/12/1999 | 10/12/1999 | 10/12/1999 | P | PART |
Jim Sly
|
|
|
after 3 pm Call first ###-#### Shear wall ok.
|
BLD-Framing/Rough-in | 10/8/1999 | 10/11/1999 | 10/11/1999 | A | FAIL |
Jim Sly
|
|
|
shear Sheila ###-#### c/n need appr. Plans for shear insp
|
INSP - Foundation | 8/24/1999 | 8/25/1999 | 8/25/1999 | A | PASS |
Jim Sly
|
|
|
08/25/99 316 - appears OK
|
INSP - Foundation | 8/23/1999 | 8/23/1999 | 8/23/1999 | P | PART |
Jim Sly
|
|
|
08/23/99 316 - Foot and rebar appear OK
|