BLD-Final | 12/23/1999 | 12/23/1999 | 12/23/1999 | P | PASS |
|
|
|
Scheduled by a contractor via Hello! on 12/23/1999 at 10:35:22. Contact: ###-####. L/C issued #18273.
|
FIRE-Final Inspection | 12/23/1999 | 12/23/1999 | 12/23/1999 | A | PASS |
Rick Jackson
|
|
|
shell complete
|
BLD-Other | 12/16/1999 | 12/17/1999 | 12/17/1999 | A | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 12/16/1999 at 14:23:28. Contact: . Not ready for inspection.
|
BLD-Final | 12/15/1999 | 12/16/1999 | 12/15/1999 | A | CANC |
|
|
|
Scheduled by a contractor via Hello! on 12/15/1999 at 15:30:37. Contact: . Disp set to [CANC] by a contractor via Hello! on 12/15/1999 at 15:51:01.
|
FIRE-Final Inspection | 12/15/1999 | 12/15/1999 | 12/15/1999 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/15/1999 at 10:20:32. Contact: ###-####. Complete sprinklers in west warehouse.
|
FIRE-Final Inspection | 12/9/1999 | 12/9/1999 | 12/9/1999 | P | FAIL |
Rick Jackson
|
|
|
sprinklers not complete
|
BLD-Conference | 12/2/1999 | 12/3/1999 | 12/3/1999 | P | PASS |
|
|
|
Scheduled by a contractor via Hello! on 12/02/1999 at 13:26:23. Contact: ###-####. Ok to pour grout.
|
BLD-Conference | 12/1/1999 | 12/2/1999 | 12/2/1999 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 12/01/1999 at 10:27:28. Contact: ###-####. R-bar placed ok to pour 2nd lift.
|
BLD-Other | 11/30/1999 | 12/1/1999 | 12/1/1999 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 11/30/1999 at 09:59:39. Contact: ###-####. R-bar placed 1st bond bewn. Ok to grout.
|
BLD-Conference | 11/22/1999 | 11/22/1999 | 11/22/1999 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 11/22/1999 at 10:50:02. Contact: ###-####. Made ok to pour cooler footings R-bar placed alley cleaned up.
|
BLD-Other | 10/18/1999 | 10/19/1999 | 10/20/1999 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 10/18/1999 at 17:00:26. Contact: ###-####. Roof shear nailing/ strapping
|
BLD-Concrete | 10/14/1999 | 10/15/1999 | 10/15/1999 | P | PART |
|
|
|
made ok for roof strapsScheduled by a contractor via Hello! on 10/14/1999 at 15:17:24. Contact: .
|
BLD-Other | 10/14/1999 | 10/15/1999 | 10/15/1999 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 10/14/1999 at 15:15:34. Contact: . Need eng/wall schedule for straps wall to roof. Top cap on walls
|