BLD-Final | 9/5/2000 | 9/6/2000 | 9/6/2000 | A | PASS |
Tony Young
|
|
|
Kristen ###-####
final occupancy ok, temp. windows are in ...... c of c # 19719 issued 9/6/2000 9:48:45 AM
|
BLD-Final | 7/3/2000 | 7/5/2000 | 7/5/2000 | A | PART |
Tony Young
|
|
|
###-#### temp occ. ok verify other sign offs tempered windows on order 7/5/00 11:47:51 AM
|
BLD-Final | 6/26/2000 | 6/30/2000 | 6/30/2000 | A | FAIL |
Tony Young
|
|
|
Kristen ###-#### elec. sign off needs done-temp glass on order 7/3/00 8:32:35 AM
|
BLD-Conference | 6/26/2000 | 6/27/2000 | 6/27/2000 | A | N/A |
Tony Young
|
|
|
Kristen ###-#### purch list for final left on site 6/27/00 2:13:44 PM
|
BLD-Grading Inspection | 6/22/2000 | | 6/22/2000 | | PASS |
Rita DeYoung
|
|
|
grading and drainage per plan and approved for final
|
BLD-Energy code compliance | 2/29/2000 | 2/29/2000 | 2/29/2000 | P | PASS |
Russ Owen
|
|
|
Kristen ###-#### please call before you go out
|
BLD-Framing/Rough-in | 2/29/2000 | 2/29/2000 | 2/29/2000 | P | PASS |
Russ Owen
|
|
|
kristen ###-#### please call before you go out
|
BLD-Framing/Rough-in | 2/23/2000 | 2/23/2000 | 2/23/2000 | P | CANC |
Russ Owen
|
|
|
call first Craig ###-#### Items will be re-inspected at insulation. 2/24/00 1:26:53 PM
|
BLD-Framing/Rough-in | 2/22/2000 | 2/22/2000 | 2/22/2000 | P | FAIL |
Russ Owen
|
|
|
Kristen, ###-#### Still has corrections, ok to insulate 2/23/00 2:05:48 PM
|
BLD-Framing/Rough-in | 2/11/2000 | 2/14/2000 | 2/14/2000 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/11/2000 at 12:10:30. Contact: ###-####. C/N posted, also fire sprinklers are not approved. 2/14/00 2:19:27 PM
|
BLD-Framing/Rough-in | 2/7/2000 | 2/7/2000 | 2/7/2000 | P | FAIL |
Wes Worcester
|
|
|
Fire sprinkler not done- per Russ and memo call for frame after fire sprinkler inspection.
|
BLD-Framing/Rough-in | 2/2/2000 | 2/3/2000 | 2/3/2000 | P | NR |
Russ Owen
|
|
|
kristen ###-#### call first to meet there
|
BLD-Framing/Rough-in | 1/27/2000 | 1/27/2000 | 1/27/2000 | A | PASS |
Wes Worcester
|
|
|
Shear walls ok.
|
BLD-Framing/Rough-in | 1/26/2000 | 1/26/2000 | 1/26/2000 | P | FAIL |
Wes Worcester
|
|
|
shear wall insp ###-#### $42.00 fee due- staples to be 2" O/C- actually 4-6" O/C. Hold down all thread pulled up by hand for HD in rear of bath. 2/7/00 8:36:55 AM
|
BLD-Framing/Rough-in | 1/20/2000 | 1/21/2000 | 1/21/2000 | A | FAIL |
Wes Worcester
|
|
|
###-#### Shear to be approved by designing engineer. 1/25/00 12:11:09 PM
|
BLD-Framing/Rough-in | 1/19/2000 | 1/19/2000 | 1/19/2000 | P | FAIL |
Wes Worcester
|
|
|
shear ###-#### Not to plan. 1/20/00 9:21:56 AM
|
BLD-Framing/Rough-in | 1/11/2000 | 1/13/2000 | 1/13/2000 | A | FAIL |
Russ Owen
|
|
|
Need to be there at 9:00 to meet with the engineer, please. ###-#### - Kristen - she will bring you a donut if you're on time! Meet engineer on site, and went over items that need to be corrected.
|
BLD-Framing/Rough-in | 1/10/2000 | 1/10/2000 | 1/10/2000 | P | FAIL |
Wes Worcester
|
|
|
Will be calling you to set up appt. time so engineer can be there, too. No contact #, no call, no one at site.
|
BLD-Footing | 9/20/1999 | 9/20/1999 | 9/20/1999 | P | PASS |
Wes Worcester
|
|
|
jed ###-####-20153
|
INSP - Foundation | 9/13/1999 | 9/13/1999 | 9/13/1999 | P | FAIL |
Wes Worcester
|
|
|
NEED REBAR INSTALLED
|