BLD-Final | 12/1/1999 | 12/2/1999 | 12/2/1999 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/01/1999 at 16:16:08. Contact: ###-####.
|
BLD-Final | 12/2/1999 | 12/2/1999 | 12/2/1999 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/02/1999 at 11:10:38. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/26/1999 | 10/26/1999 | 10/26/1999 | A | PASS |
Jim Storey
|
|
|
Ok for cover
|
BLD-Framing/Rough-in | 10/21/1999 | 10/21/1999 | 10/21/1999 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 10/21/1999 at 11:22:40. Contact: ###-####. $42.00 reinspection fee- prior C/N not completed EnG. For garage fix to be on jobsite no answer at contact.
|
BLD-Energy code compliance | 10/19/1999 | 10/19/1999 | 10/19/1999 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/19/1999 at 07:23:23. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/15/1999 | 10/15/1999 | 10/15/1999 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/15/1999 at 07:15:05. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/1/1999 | 10/1/1999 | 10/1/1999 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/01/1999 at 10:01:33. Contact: ###-####.\\ok to side
|
INSP - Foundation | 9/9/1999 | 9/9/1999 | 9/9/1999 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/09/1999 at 07:00:47. Contact: ###-####. 9/9 entered pass. jrb
|
Footing | 9/8/1999 | 9/8/1999 | 9/8/1999 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/08/1999 at 06:25:21. Contact: ###-####. 9/8 NR. jrb
|
INSP - Foundation | 9/8/1999 | 9/8/1999 | 9/8/1999 | P | PASS |
Russ Owen
|
|
|
jeremy ###-#### footing; 9/8 Footings only at this time. jrb
|