BLD-Final | 1/9/2000 | 1/10/2000 | 1/10/2000 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 01/09/2000 at 17:52:17. Contact: . Need mechanical and plumbing.
|
BLD-Final | 1/10/2000 | 1/10/2000 | 1/10/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 10:39:06. Contact: . L/C.
Trrrr
|
BLD-Final | 1/6/2000 | 1/7/2000 | 1/7/2000 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/06/2000 at 14:41:32. Contact: . C/N & plm.
|
BLD-Footing | 10/6/1999 | 10/6/1999 | 1/3/2000 | A | PASS |
Jim Storey
|
|
|
###-#### bill reinspection made ok with insp. done at latter date. 301
|
BLD-Energy code compliance | 11/19/1999 | 11/22/1999 | 11/22/1999 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/19/1999 at 14:48:47. Contact: . Backing on Interior fire wall ok need 5/8 gyp. Installed.
|
BLD-Wall cover | 11/18/1999 | 11/18/1999 | 11/18/1999 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/18/1999 at 11:12:25. Contact: ###-####. N/R.
|
BLD-Energy code compliance | 11/16/1999 | 11/17/1999 | 11/17/1999 | P | PASS |
Jim Storey
|
|
|
KEN ###-#### ENERGY CODE
|
BLD-Framing/Rough-in | 11/16/1999 | 11/17/1999 | 11/17/1999 | P | PART |
Jim Storey
|
|
|
KEN ###-#### RE-INSP FR Call for interior fire wall inspection above ceiling line/firechalk.
|
BLD-Framing/Rough-in | 11/16/1999 | 11/16/1999 | 11/16/1999 | P | FAIL |
Jim Storey
|
|
|
KEN ###-#### FR INSP Fire wall & fire block fireplace ceiling.
|
BLD-Foundation | 10/8/1999 | 10/11/1999 | 10/11/1999 | A | PASS |
Jim Storey
|
|
|
Ken ###-####
|
BLD-Foundation | 10/8/1999 | 10/8/1999 | 10/7/1999 | P | PASS |
Jim Storey
|
|
|
As per approved plan.
|
BLD-Foundation | 10/7/1999 | 10/7/1999 | 10/7/1999 | P | FAIL |
Wes Worcester
|
|
|
ken coffey--###-#### found wall need plan, compaction report and rebar per detail
|
BLD-Concrete | 10/6/1999 | 10/6/1999 | 10/6/1999 | P | FAIL |
Wes Worcester
|
|
|
###-####--- SHELBY CONCRETE WALL INSP stop work issued
|
BLD-Footing | 10/4/1999 | 10/5/1999 | 10/5/1999 | A | FAIL |
Russ Owen
|
|
|
Shelby ###-#### rebar splices, no good clearances to earth and form no good
|
BLD-Footing | 10/5/1999 | 10/5/1999 | 10/5/1999 | P | PART |
Russ Owen
|
|
|
Ken ###-#### footing ok but have not yet received compaction report, told contractor I must have this with a wall inspection
|
BLD-Footing | 10/1/1999 | 10/4/1999 | 10/4/1999 | A | FAIL |
Russ Owen
|
|
|
###-####--SHELBY ---FT RE-INSP prior to correction of compaction report needed , also rebar required throught out by approved plans, not done.
|
BLD-Footing | 9/30/1999 | 10/1/1999 | 10/1/1999 | A | FAIL |
Jim Storey
|
|
|
###-####/shelby ft Cert for compaction of imported fill
|