Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-02521
StatusFinaled
Name MIDDLETON WILLIAM C
Site Address 612 W SYLVAN CT
Project NameBOCAGE PLACE
Customer Number 
ePlanReviewNo
Description
TO CONSTRUCT A NEW, TYPE "B" UNIT, SINGLE STORY, WOOD FRAMED, THREE BEDROOM, TWO BATH 1,452 SQ.FT. TOWNHOME WITH AN ATTACHED 390 SQ.FT. GARAGE, ON ZERO LOT LINE. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST AND THE 1997 EDITION OF THE UBC. MJP P.C.# 665
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/9/20001/10/20001/10/2000ANR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 01/09/2000 at 17:52:17. Contact: . Need mechanical and plumbing.
BLD-Final1/10/20001/10/20001/10/2000PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/10/2000 at 10:39:06. Contact: . L/C.

Trrrr
BLD-Final1/6/20001/7/20001/7/2000PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/06/2000 at 14:41:32. Contact: . C/N & plm.
BLD-Footing10/6/199910/6/19991/3/2000APASS
DetailsJim Storey
###-#### bill reinspection made ok with insp. done at latter date. 301
BLD-Energy code compliance11/19/199911/22/199911/22/1999APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/19/1999 at 14:48:47. Contact: . Backing on Interior fire wall ok need 5/8 gyp. Installed.
BLD-Wall cover11/18/199911/18/199911/18/1999PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/18/1999 at 11:12:25. Contact: ###-####. N/R.
BLD-Energy code compliance11/16/199911/17/199911/17/1999PPASS
DetailsJim Storey
KEN ###-#### ENERGY CODE
BLD-Framing/Rough-in11/16/199911/17/199911/17/1999PPART
DetailsJim Storey
KEN ###-#### RE-INSP FR Call for interior fire wall inspection above ceiling line/firechalk.
BLD-Framing/Rough-in11/16/199911/16/199911/16/1999PFAIL
DetailsJim Storey
KEN ###-#### FR INSP Fire wall & fire block fireplace ceiling.
BLD-Foundation10/8/199910/11/199910/11/1999APASS
DetailsJim Storey
Ken ###-####
BLD-Foundation10/8/199910/8/199910/7/1999PPASS
DetailsJim Storey
As per approved plan.
BLD-Foundation10/7/199910/7/199910/7/1999PFAIL
DetailsWes Worcester
ken coffey--###-#### found wall need plan, compaction report and rebar per detail
BLD-Concrete10/6/199910/6/199910/6/1999PFAIL
DetailsWes Worcester
###-####--- SHELBY CONCRETE WALL INSP stop work issued
BLD-Footing10/4/199910/5/199910/5/1999AFAIL
DetailsRuss Owen
Shelby ###-#### rebar splices, no good clearances to earth and form no good
BLD-Footing10/5/199910/5/199910/5/1999PPART
DetailsRuss Owen
Ken ###-#### footing ok but have not yet received compaction report, told contractor I must have this with a wall inspection
BLD-Footing10/1/199910/4/199910/4/1999AFAIL
DetailsRuss Owen
###-####--SHELBY ---FT RE-INSP prior to correction of compaction report needed , also rebar required throught out by approved plans, not done.
BLD-Footing9/30/199910/1/199910/1/1999AFAIL
DetailsJim Storey
###-####/shelby ft Cert for compaction of imported fill