BLD-Final | 11/8/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Jim Sly
|
|
|
Scott ###-#### C/C #16260
|
BLD-Final | 11/4/1999 | 11/4/1999 | 11/4/1999 | P | FAIL |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 11/04/1999 at 10:47:52. Contact: ###-####. Left C/N
|
BLD-Energy code compliance | 9/30/1999 | 9/30/1999 | 9/30/1999 | P | PASS |
Jim Sly
|
|
|
MIKE ###-####
|
BLD-Framing/Rough-in | 9/30/1999 | 9/30/1999 | 9/30/1999 | P | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 9/29/1999 | 9/29/1999 | 9/29/1999 | P | FAIL |
Jim Sly
|
|
|
MIKE ###-#### C/N.. Nail hanger, brace gable, block trusses
|
BLD-Framing/Rough-in | 9/24/1999 | 9/24/1999 | 9/27/1999 | P | PART |
Tom Arcoraci
|
|
|
sheer wall Mike ###-#### Ok to side
|
INSP - Foundation | 9/8/1999 | 9/8/1999 | 9/8/1999 | | PASS |
|
|
|
add - dupe w 9/7 pm inspctn, corr to entry error on 9/7 caused prblm, inspctr went out twice
|
INSP - Foundation | 9/7/1999 | 9/7/1999 | 9/7/1999 | P | PASS |
Jim Sly
|
|
|
tony ###-#### ft insp; 9/7 Footing and rebar OK. jrb
|