BLD-Final | 12/21/1999 | 12/22/1999 | 12/22/1999 | A | FAIL |
Alan Hauser
|
|
|
john ###-#### key over front door Done by #407.
|
BLD-Final | 12/22/1999 | 12/22/1999 | 12/22/1999 | P | PASS |
Russ Owen
|
|
|
Letter from Ashley Glass will replace rear window next to door, to temp. glass, signed by John of Stetson homes.
|
BLD-Final | 12/20/1999 | 12/21/1999 | 12/21/1999 | A | FAIL |
Alan Hauser
|
|
|
###-#### key will be above front door Done by #407.
|
BLD-Final | 12/21/1999 | 12/21/1999 | 12/21/1999 | A | FAIL |
Russ Owen
|
|
|
Temp. glass, under floor vapor barrier.
|
BLD-Energy code compliance | 11/12/1999 | 11/12/1999 | 11/12/1999 | P | PASS |
Russ Owen
|
|
|
john ###-#### Ok to sheetrock.
|
BLD-Framing/Rough-in | 11/9/1999 | 11/9/1999 | 11/9/1999 | P | PASS |
Russ Owen
|
|
|
|
BLD-Framing/Rough-in | 11/8/1999 | 11/9/1999 | 11/9/1999 | A | PART |
Russ Owen
|
|
|
John ###-#### Corrections ok, need energy seal done.
|
BLD-Framing/Rough-in | 11/5/1999 | 11/5/1999 | 11/5/1999 | P | FAIL |
Russ Owen
|
|
|
JOHN-- ###-#### FR INSP
|
BLD-Framing/Rough-in | 10/26/1999 | 10/27/1999 | 10/27/1999 | A | PART |
Tom Arcoraci
|
|
|
###-#### Ok to side Eng. Ok'ed strap
|
BLD-Framing/Rough-in | 10/25/1999 | 10/26/1999 | 10/26/1999 | A | FAIL |
Wes Worcester
|
|
|
shear nailing john ###-#### Not to plan
|
BLD-Foundation | 10/8/1999 | 10/8/1999 | 10/8/1999 | P | PASS |
Wes Worcester
|
|
|
foundation wall Chris ###-####
|
BLD-Footing | 10/6/1999 | 10/7/1999 | 10/7/1999 | A | PASS |
Russ Owen
|
|
|
chris ###-####
|