BLD-Final | 12/7/1999 | 12/7/1999 | 12/7/1999 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/07/1999 at 10:17:34. Contact: ###-####.
|
BLD-Final | 12/7/1999 | 12/7/1999 | 12/7/1999 | A | PASS |
Carl Dependahl
|
|
|
|
FIRE-Final Inspection | 12/6/1999 | 12/7/1999 | 12/7/1999 | A | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/06/1999 at 14:10:28. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/26/1999 | 11/29/1999 | 11/29/1999 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/26/1999 at 10:02:54. Contact: ###-####. C/N; beams.
|
BLD-Concrete | 11/9/1999 | 11/10/1999 | 11/10/1999 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/09/1999 at 09:31:47. Contact: ###-####.
|
BLD-Conference | 11/4/1999 | 11/4/1999 | 11/4/1999 | A | PART |
|
|
|
With Gen. contractor on req. insp. by other inspectors- must call for inspection that is needed not to guess.
|
BLD-Footing | 11/3/1999 | 11/4/1999 | 11/4/1999 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 11/03/1999 at 12:25:11. Contact: ###-####. Ok by #340
|
BLD-Foundation | 11/3/1999 | 11/4/1999 | 11/4/1999 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 11/03/1999 at 12:32:45. Contact: ###-####. OK by #340
|
BLD-Foundation | 11/2/1999 | 11/2/1999 | 11/2/1999 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/02/1999 at 11:03:15. Contact: ###-####. Need steel @ cells. Recall.
|
BLD-Footing | 10/18/1999 | 10/18/1999 | 10/18/1999 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/18/1999 at 11:24:30. Contact: ###-####. Carport ftgs.; eng. To follow for columns etc.
|