BLD-Final | 3/29/2000 | 3/29/2000 | 3/29/2000 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/29/2000 at 09:06:11. Contact: . Contractor is providing drainage. 3/30/00 10:53:08 AM
|
BLD-Final | 3/27/2000 | 3/28/2000 | 3/28/2000 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/27/2000 at 16:26:59. Contact: ###-####. drainage and frost depth. Also drain to other lots? 3/28/00 1:31:26 PM
|
BLD-Framing/Rough-in | 1/27/2000 | 1/28/2000 | 1/28/2000 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 01/27/2000 at 13:39:09. Contact: ###-####. c/n removed ok to cover 2/1/00 8:54:47 AM
|
BLD-Framing/Rough-in | 1/25/2000 | 1/27/2000 | 1/27/2000 | A | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 01/25/2000 at 21:39:07. Contact: ###-####. c/n of 325 not complete yet 2/14/00 10:52:50 AM
|
BLD-Framing/Rough-in | 1/26/2000 | 1/26/2000 | 1/25/2000 | P | PART |
Wes Worcester
|
|
|
CN issued for framing, ok'd to insulate.
|
BLD-Framing/Rough-in | 1/21/2000 | 1/24/2000 | 1/24/2000 | A | FAIL |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 01/21/2000 at 14:24:12. Contact: ###-####. Not to plan, over heigth wall, truss eng. not done. 1/25/00 1:30:47 PM
|
BLD-Framing/Rough-in | 1/10/2000 | 1/11/2000 | 1/11/2000 | A | PASS |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 11:14:14. Contact: ###-####. Shear ok.
|
BLD-Foundation | 12/21/1999 | 12/21/1999 | 12/21/1999 | A | PASS |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 12/21/1999 at 05:55:01. Contact: ###-####.
|
BLD-Footing | 12/20/1999 | 12/20/1999 | 12/20/1999 | P | PASS |
|
|
|
Scheduled by a contractor via Hello! on 12/20/1999 at 10:37:34. Contact: ###-####. Setbacks ok forms set.
|