Final | 6/30/2000 | 7/5/2000 | 7/5/2000 | A | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 06/30/2000 at 14:38:05. Contact: ###-####. Ok final 7/7/00 12:56:41 PM
|
Final | 6/29/2000 | 6/30/2000 | 6/30/2000 | A | FAIL |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 06/29/2000 at 12:57:46. Contact: ###-####. no access 7/3/00 8:20:23 AM
|
Final | 6/28/2000 | 6/29/2000 | 6/29/2000 | A | FAIL |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 06/28/2000 at 13:50:02. Contact: ###-####. nec no GFCI outlet within 25' of roof equipment 6/29/00 12:53:24 PM
|
Final | 6/20/2000 | 6/20/2000 | 6/20/2000 | P | FAIL |
Marv Burrus
|
|
|
###-#### DAVE No access; called contractor, used wrong case number, and contractor didn't perform roof-top A/C unit installation. 6/21/00 11:30:59 AM
|
Final | 5/16/2000 | 5/16/2000 | 5/16/2000 | P | FAIL |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 05/16/2000 at 08:09:04. Contact: ###-####. Final swamp coolers no roof access fail. 5/17/00 1:49:44 PM
|
Final | 3/27/2000 | 3/28/2000 | 3/28/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 03/27/2000 at 08:16:43. Contact: ###-####. Temp. occ. 3/28/00 11:51:08 AM
|
Electrical Rough-In | 2/7/2000 | 2/8/2000 | 2/8/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 02/07/2000 at 13:23:36. Contact: ###-####. 2 bathrooms and concession room ele r/I
|